10572 W BLYTHE AVE 90064
Certificate Information: 10572 W BLYTHE AVE 90064
- Application / Permit
- 22010-10000-01760
- Plan Check / Job No.
- B22LA06251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO-CAR GARAGE. 1 OF 2
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | ADRIANA LOPEZ |
| Corrections Issued | 4/30/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 5/12/2022 | KEN GILL |
| Building Plans Picked Up | 5/13/2022 | APPLICANT |
| Applicant returned to address corrections | 6/15/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/8/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 7/12/2022 | ADRIANA LOPEZ |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 3/12/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 3/18/2024 | DANIEL ORRANTE |
| CofO Issued | 3/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/5/2022 | VALERIA CEJA |
| Specific Plan | Cleared | 5/5/2022 | VALERIA CEJA |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | CATHERINE ADROVER |
| Permit | Cleared | 5/6/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 5/9/2022 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 5/16/2022 | RUEL COLE |
| Low Impact Development | Cleared | 6/24/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | DINAH GARIN |
| GPI Written Notices | Cleared | 7/8/2022 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/22/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 9/22/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 9/22/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/5/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/11/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 11/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 12/16/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/31/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/31/2023 | Approved | JESUS RODRIGUEZ |
| Sewer | 2/13/2023 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 2/13/2023 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 2/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 3/24/2023 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 4/6/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/6/2023 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 4/10/2023 | Partial Approval | ASHLEY THOMPSON |
| Final | 4/10/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 4/10/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 4/10/2023 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | CLAYTON GRAHAM |
| Deputy Wood Construction | 4/21/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 4/21/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/1/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 5/3/2023 | Approved | CLAYTON GRAHAM |
| Gas Test | 8/24/2023 | Approved | CLAYTON GRAHAM |
| Special/Order Compliance | 9/21/2023 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 9/27/2023 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 12/1/2023 | Partial Approval | MICHAEL PELHAM |
| ELECTRICAL-Final | 2/23/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 2/23/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/23/2024 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 2/26/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 2/27/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 3/12/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 3/12/2024 | Approved | OGANES TARAKHCHYAN |