3115 S ORCHARD AVE 90007
Certificate Information: 3115 S ORCHARD AVE 90007
- Application / Permit
- 22010-10000-01745
- Plan Check / Job No.
- B22LA06146
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NEW STATE APPROVED MODULAR BUILDING FOR HOUSING SUPPORTIVE OFFICES. RESTRIPE PARKING LOT. 1 OF 2
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Green Plans Picked Up | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | ALBERT SERVIN |
| Corrections Issued | 4/25/2022 | ALBERT SERVIN |
| Quality Review Completed | 4/27/2022 | KEN GILL |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| Applicant returned to address corrections | 7/5/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 7/29/2022 | ALBERT SERVIN |
| Plan Check Approved | 3/30/2023 | ALBERT SERVIN |
| Plan Check Approved | 4/19/2023 | ALBERT SERVIN |
| Issued | 4/20/2023 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 5/13/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/13/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/13/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/13/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/13/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/13/2022 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 7/16/2022 | GILBERT URREA |
| Green Code | Cleared | 7/26/2022 | MICHAEL AYERS |
| DAS Clearance | Cleared | 9/1/2022 | ALBERT SERVIN |
| Low Impact Development | Cleared | 9/28/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/11/2022 | STEVE MELGAR |
| Historic Resource Verification | Cleared | 3/3/2023 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 3/3/2023 | GRACIELA ACOSTA |
| Address approval | Cleared | 3/10/2023 | AMAAN MALIK |
| Specific Plan | Cleared | 3/13/2023 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 3/14/2023 | AMAAN MALIK |
| Highway dedication | Cleared | 3/31/2023 | JEANIE LAM |
| Miscellaneous | Cleared | 4/5/2023 | MAXFIELD VERMY |
| Prkng lot landscape/Water mgmt | Cleared | 4/5/2023 | MAXFIELD VERMY |
| Disturb/Remove Protected Trees | Cleared | 4/17/2023 | ADALBERTO VERA |
| Permit | Cleared | 4/19/2023 | STEVE MELGAR |
Contact Information
| Architect | Hamner,, Derek Michael; Lic. No.: C19023 | 1131 KENTON DRIVE MONTEREY PARK, CA 91755 |
| Contractor | Vancrest Construction Corp; Lic. No.: 393800-B | 7171 NORTH FIGUEROA STREET LOS ANGELES, CA 90042 |
| Engineer | Bornand,, Christophe N; Lic. No.: C80596 | 3582 VETERAN AVE LOS ANGELES, CA 90034 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2023 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Barrier | 5/30/2023 | Partial Inspection | RAFAEL ESPINOZA |
| METHANE-Subgrade | 5/30/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Piling/Pier/Caisson | 5/30/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 6/2/2023 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 6/2/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Subgrade | 6/2/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/9/2023 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 6/9/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 6/9/2023 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 8/14/2023 | Partial Approval | RAFAEL ESPINOZA |
| METHANE-Barrier | 8/14/2023 | Partial Inspection | RAFAEL ESPINOZA |
| METHANE-Subgrade | 8/14/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 8/14/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Piling/Pier/Caisson | 9/8/2023 | Partial Approval | EDWIN GREGORYONA |
| Green Building Final | 11/2/2023 | Approved | JAMES POWERS |
| Green Building Rough | 11/2/2023 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Not Ready | JAMES POWERS |