5353 N MONTEREY ROAD 90042

Certificate Information: 5353 N MONTEREY ROAD 90042

Application / Permit
22010-10000-01742
Plan Check / Job No.
B22LA06141
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU 639 SF OVER 2-CAR GARAGE 559 SF (TOTAL RFA=998 SF). ADU PER STATE LAW. 2 OF 3
Permit Issued
Issued on 7/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 CHUNG-WEN CHUANG
Corrections Issued 5/24/2022 CHUNG-WEN CHUANG
Quality Review Completed 6/2/2022 SAI KHUM
Building Plans Picked Up 6/9/2022 APPLICANT
Applicant returned to address corrections 6/15/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 7/27/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 9/7/2022 CHUNG-WEN CHUANG
Applicant returned to address corrections 5/11/2023 CHUNG-WEN CHUANG
Applicant returned to address corrections 5/18/2023 CHUNG-WEN CHUANG
Applicant returned to address corrections 6/2/2023 CHUNG-WEN CHUANG
Applicant returned to address corrections 6/8/2023 CHUNG-WEN CHUANG
Plan Check Approved 7/6/2023 CHUNG-WEN CHUANG
Issued 7/28/2023 APPLICANT
CofO in Progress 10/22/2025 DAVID WILLIAMS
Permit Finaled 10/23/2025 DEROLD HAUFF
CofO Issued 10/23/2025 DEROLD HAUFF
Permit Finaled 10/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/15/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 6/15/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 6/15/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 6/15/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 6/15/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 6/15/2022 JEANIE LAM
Permit Cleared 6/15/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/16/2022 JEANIE LAM
Sewer availability Cleared 6/28/2022 TREVOR QUAN
Trees in Parkway Cleared 8/25/2022 ADALBERTO VERA
Disturb/Remove Protected Trees Cleared 9/13/2022 ADALBERTO VERA
Low Impact Development Cleared 10/31/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 11/4/2022 AMAAN MALIK
Hydrant and Access approval Cleared 11/13/2022 JOHN CONNEALLY
"D" conditions Cleared 4/17/2023 RUBEN VASQUEZ
"Q" conditions Cleared 4/17/2023 RUBEN VASQUEZ
GPI Written Notices Cleared 6/8/2023 CHUNG-WEN CHUANG
Grading Pre-Inspection Cleared 6/8/2023 CHUNG-WEN CHUANG

Contact Information

Architect Fenlon,, Martin Richard; Lic. No.: C29965 5526 MONTEREY ROAD      LOS ANGELES, CA 90042
Contractor John Wendell L; Lic. No.: 1034536-B 15330 ARCHWOOD ST      VAN NUYS, CA 91406
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010
Engineer Mcgrath,, Michael; Lic. No.: C86488 6092 KELSEY CIRCLE      HUNTINGTON BEACH, CA 92647
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835
Geologist Romanowski,, Walter; Lic. No.: EG1942 14533 CALPELLA STREET      LA MIRADA, CA 906383709

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/3/2023 Partial Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 3/28/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/28/2024 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/24/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 5/14/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/14/2024 Partial Approval JOSEPH MCGARRY
Deputy Steel/Welding 6/3/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 10/2/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 12/24/2024 No Access for Inspection LILIANA PORTILLO
PLUMBING-Rough 12/24/2024 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 12/27/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 12/27/2024 Approved ALIZAH MAYAGOITIA
Shower Pan 12/27/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/16/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 1/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
Interior/Exterior Lathing 1/16/2025 Partial Approval NICHOLAS LOPEZ
HVAC-Rough 1/22/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 2/3/2025 Corrections Issued LILIANA PORTILLO
Green Building Rough 2/3/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 2/3/2025 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 2/3/2025 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 2/3/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Corrections Issued LILIANA PORTILLO
Insulation 2/5/2025 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 2/5/2025 Partial Approval LILIANA PORTILLO
Drywall Nailing 2/7/2025 Corrections Issued LILIANA PORTILLO
Green Building Rough 2/7/2025 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 2/7/2025 Approved LILIANA PORTILLO
Shower Pan 2/7/2025 Approved LILIANA PORTILLO
Drywall Nailing 2/11/2025 Partial Approval LILIANA PORTILLO
Green Building Rough 2/11/2025 Partial Approval LILIANA PORTILLO
HVAC-Rough 2/11/2025 Not Ready for Inspection LILIANA PORTILLO
Insulation 2/11/2025 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 4/23/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 4/23/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 4/23/2025 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 4/23/2025 Corrections Issued BRENDAN MORELLI
Insulation 4/23/2025 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 4/30/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 4/30/2025 Approved LILIANA PORTILLO
Green Building Rough 4/30/2025 Approved LILIANA PORTILLO
HVAC-Rough 4/30/2025 Approved LILIANA PORTILLO
Insulation 4/30/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 4/30/2025 Approved LILIANA PORTILLO
Drywall Nailing 5/5/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/29/2025 Not Ready for Inspection LILIANA PORTILLO
Final 5/29/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 5/29/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 5/29/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 5/29/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Not Required LILIANA PORTILLO
Service/Power Release 5/29/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/29/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/2/2025 Corrections Issued LILIANA PORTILLO
Service/Power Release 6/2/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 6/10/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 6/10/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 6/13/2025 Approved LILIANA PORTILLO
Service/Power Release 6/13/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 6/24/2025 Approved LILIANA PORTILLO
Final 9/30/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 9/30/2025 Approved LILIANA PORTILLO
Reinforced Masonry Frame 9/30/2025 Approved LILIANA PORTILLO
Final 10/9/2025 Corrections Issued LILIANA PORTILLO
Final 10/10/2025 Corrections Issued LILIANA PORTILLO
Final 10/21/2025 OK to Issue CofO DAVID WILLIAMS