1356 W BLAKE AVE 90031
Certificate Information: 1356 W BLAKE AVE 90031
- Application / Permit
- 22010-10000-01739
- Plan Check / Job No.
- B22LA06134
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ADU WITH ROOF DECK AREA PER CA GOVT. CODE
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/28/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/5/2022 | SAI KHUM |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Applicant returned to address corrections | 6/10/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 12/6/2022 | MAHNAZ NOURHASHEMI |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 9/13/2023 | THOMAS LOGRASSO |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2022 | CINDY QI |
| ZI | Cleared | 6/28/2022 | JASON CHAN |
| Sewer availability | Cleared | 6/29/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 8/25/2022 | GILBERT URREA |
| Construction near power lines | Cleared | 9/21/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/3/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/4/2022 | AMAAN MALIK |
| Permit | Cleared | 10/11/2022 | CHRISTOPHER ROCHA |
| Trees in Parkway | Cleared | 11/16/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/20/2022 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/19/2023 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/23/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/22/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 2/22/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/24/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/24/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 2/24/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 2/24/2023 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Rough | 2/24/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/24/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/2/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/6/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 3/6/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/7/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/7/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/7/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 3/7/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 3/7/2023 | Approved | DONALD CRICHLOW |
| Insulation | 3/13/2023 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 3/15/2023 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/21/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 3/21/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 3/21/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 3/21/2023 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Rough | 3/21/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/28/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 4/3/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 4/14/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/20/2023 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 4/26/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 6/9/2023 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/20/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/15/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 8/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 8/15/2023 | Approved | THOMAS LOGRASSO |
| Final | 8/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 8/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 9/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 9/11/2023 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 9/11/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 9/13/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 9/13/2023 | Approved | THOMAS LOGRASSO |