1186 N CORSICA DR 90272

Certificate Information: 1186 N CORSICA DR 90272

Application / Permit
22010-10000-01733
Plan Check / Job No.
B22LA06109
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH BASEMENT AND ATTACHED 3-CAR GARAGE.
Permit Issued
Issued on 2/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 MAHNAZ NOURHASHEMI
Corrections Issued 5/6/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 5/12/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/17/2022 APPLICANT
Applicant returned to address corrections 9/7/2022 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 12/23/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 1/26/2023 MAHNAZ NOURHASHEMI
Issued 2/8/2023 APPLICANT
CofO in Progress 11/4/2025 HERBERT GIRON
Permit Finaled 11/10/2025 RICHARD STEINBACH
CofO Issued 11/10/2025 RICHARD STEINBACH
Permit Finaled 11/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 5/31/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 6/28/2022 SAUL GARCIA
Sewer availability Cleared 6/28/2022 SAUL GARCIA
Trees in Parkway Cleared 7/13/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 7/29/2022 KURT CORRAL
Low Impact Development Cleared 12/6/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 12/7/2022 SAUL GARCIA
GPI Written Notices Cleared 12/23/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 12/23/2022 MAHNAZ NOURHASHEMI
Haul Route Cleared 1/13/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor Mir Construction Inc; Lic. No.: 930423-B 16656 CHAPLIN AVENUE      ENCINO, CA 91436

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2023 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 5/18/2023 Partial Approval OGANES TARAKHCHYAN
Reinforced Concrete Frame 6/13/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 7/5/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/11/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/25/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/3/2023 Approved OGANES TARAKHCHYAN
Underground Mechanical 8/8/2023 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/1/2023 Partial Approval KENNETH NAGLE
Deputy Drilled-In Anchors 10/12/2023 No Access for Inspection KENNETH NAGLE
Underground Mechanical 10/13/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/25/2023 Corrections Issued OGANES TARAKHCHYAN
Pre-Inspection 10/30/2023 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 11/1/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/3/2023 No Access for Inspection OGANES TARAKHCHYAN
Structural Steel Frame 11/3/2023 No Access for Inspection OGANES TARAKHCHYAN
Deputy Reinf. Concrete 11/6/2023 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/6/2023 Approved ARAM AVEDISIAN
Deputy Steel/Welding 11/28/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2023 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/23/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 5/9/2024 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 5/22/2024 Corrections Issued ARAM AVEDISIAN
Underground Mechanical 5/22/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 6/14/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/18/2024 Approved ARAM AVEDISIAN
Sewer 6/18/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/22/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/14/2024 Approved ARAM AVEDISIAN
Green Building Rough 8/14/2024 Not Ready for Inspection ARAM AVEDISIAN
Verify Sprinkler Sign Off 8/14/2024 Approved ARAM AVEDISIAN
Gas Test 8/23/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/26/2024 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 8/26/2024 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/6/2024 Approved JESUS RODRIGUEZ
Green Building Rough 9/6/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 9/6/2024 Approved JESUS RODRIGUEZ
Insulation 9/6/2024 Approved JESUS RODRIGUEZ
Special/Order Compliance 9/6/2024 Partial Inspection MICHAEL ALLEN
Drywall Nailing 9/16/2024 Corrections Issued KENNETH NAGLE
Drywall Nailing 9/18/2024 Approved JESUS RODRIGUEZ
Shower Pan 9/30/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/4/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 11/22/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 2/21/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 7/30/2025 Corrections Issued STEPHANIE SWANSON
Gas Test 8/12/2025 Approved HERBERT GIRON
PLUMBING-Final 8/12/2025 Partial Approval HERBERT GIRON
ELECTRICAL-Final 8/19/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/21/2025 Approved HERBERT GIRON
ELECTRICAL-Final 8/27/2025 Corrections Issued HERBERT GIRON
HVAC-Final 8/29/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/5/2025 Partial Approval HERBERT GIRON
HVAC-Final 9/8/2025 Approved HERBERT GIRON
Service/Power Release 10/8/2025 Approved KENNETH NAGLE
ELECTRICAL-Final 10/17/2025 Approved HERBERT GIRON
Final 10/17/2025 Corrections Issued HERBERT GIRON
Green Building Final 10/17/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Approved HERBERT GIRON
Smoke Detectors 10/17/2025 Approved HERBERT GIRON
Final 11/4/2025 OK to Issue CofO HERBERT GIRON