3757-3759 S DALTON AVE 90018
Certificate Information: 3757-3759 S DALTON AVE 90018
- Application / Permit
- 22010-10000-01725
- Plan Check / Job No.
- B22LA06066
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED THREE STORY DUPLEX WITH ATTACHED 4 CAR GARAGE
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 12/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 4/26/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 4/27/2022 | PETER KIM |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Applicant returned to address corrections | 9/7/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/20/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 11/4/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 11/29/2022 | ARMEN JIVALAGIAN |
| Issued | 3/10/2023 | APPLICANT |
| CofO in Progress | 12/2/2024 | SABAS ALONSO |
| Re-Activate Permit | 12/10/2024 | DEROLD HAUFF |
| CofO Issued-Status Void | 12/10/2024 | DEROLD HAUFF |
| Permit Finaled-Status Void | 12/10/2024 | DEROLD HAUFF |
| Permit Finaled | 12/10/2024 | DEROLD HAUFF |
| CofO Corrected | 12/10/2024 | DEROLD HAUFF |
| Permit Finaled | 12/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2022 | WALLIE JONG |
| Sewer availability | Cleared | 7/18/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 8/16/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 8/25/2022 | MARCO SANCHEZ |
| Permit | Cleared | 8/29/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 8/29/2022 | CINDY QI |
| SB8 RUD | Cleared | 9/26/2022 | KENNETH LE |
| Trees in Parkway | Cleared | 10/12/2022 | ADALBERTO VERA |
| Hold | Cleared | 4/14/2023 | MARIA VENDIVIL |
Contact Information
| Architect | Feagins,, Larry; Lic. No.: C27009 | 669 N THIRD AVENUE UPLAND, CA 91786 |
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/17/2023 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/29/2023 | Approved | SABAS ALONSO |
| Sewer | 8/29/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 1/11/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Conditional Approval | SABAS ALONSO |
| PLUMBING-Rough | 1/26/2024 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 3/5/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 3/5/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/12/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 3/12/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 3/12/2024 | Approved | SABAS ALONSO |
| Insulation | 3/22/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/27/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 3/27/2024 | Approved | SABAS ALONSO |
| Shower Pan | 4/11/2024 | Partial Approval | SABAS ALONSO |
| Shower Pan | 4/15/2024 | Partial Approval | BRENDAN MORELLI |
| Final | 11/21/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/21/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/21/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 11/21/2024 | Approved | SABAS ALONSO |
| Final | 11/27/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 11/27/2024 | Approved | SABAS ALONSO |