10403 N QUILL AVE 91040

Certificate Information: 10403 N QUILL AVE 91040

Application / Permit
22010-10000-01715
Plan Check / Job No.
B22LA06007
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY DETACHED SFD WITH ATTACHED ADU
Permit Issued
Issued on 12/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2022 APPLICANT
Assigned to Plan Check Engineer 4/19/2022 JAD BASMA
Corrections Issued 4/22/2022 JAD BASMA
Quality Review Completed 4/27/2022 KEN GILL
Building Plans Picked Up 5/10/2022 APPLICANT
Applicant returned to address corrections 6/2/2022 JAD BASMA
Plan Check Approved 12/23/2022 JAD BASMA
Issued 12/23/2022 APPLICANT
CofO in Progress 1/26/2024 DAVID ANDERSON
CofO in Progress 3/12/2024 DAVID ANDERSON
CofO in Progress 5/17/2024 DAVID MATSON
Permit Finaled 5/29/2024 RUBEN SALAS
CofO Issued 5/29/2024 RUBEN SALAS
Permit Finaled 5/29/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/3/2022 DAGOVERTO GUERRERO
Address approval Cleared 6/3/2022 DAGOVERTO GUERRERO
Highway dedication Cleared 6/3/2022 DAGOVERTO GUERRERO
Permit Cleared 6/3/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/7/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/7/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 6/8/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 7/16/2022 KURT CORRAL
ZI Cleared 11/1/2022 SARAH HOUNSELL
Low Impact Development Cleared 12/1/2022 DEBORA LEITE
GPI Written Notices Cleared 12/23/2022 JAD BASMA
Roof/Waste drainage to street Cleared 12/23/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 7621 LOISE AVE      ENCINO, CA 91316

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/19/2023 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 1/26/2023 Partial Approval DAVID ANDERSON
PLUMBING-Rough 1/26/2023 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 2/3/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval DAVID ANDERSON
Wood Frame 3/9/2023 Not Ready for Inspection DAVID ANDERSON
Deputy Wood Construction 4/14/2023 Conditional Approval MATTHEW NELSON
ELECTRICAL-Rough 7/17/2023 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 7/17/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 7/17/2023 Approved DAVID ANDERSON
Underground Mechanical 7/17/2023 Partial Approval DAVID ANDERSON
Wood Frame 7/17/2023 Corrections Issued DAVID ANDERSON
Insulation 8/8/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/8/2023 Approved DAVID ANDERSON
Shower Pan 8/8/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/1/2023 Approved DAVID ANDERSON
Final 12/1/2023 Corrections Issued DAVID ANDERSON
Green Building Final 12/1/2023 Approved DAVID ANDERSON
Green Building Rough 12/1/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 12/1/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 12/1/2023 Corrections Issued DAVID ANDERSON
Verify Sprinkler Sign Off 12/1/2023 Approved DAVID ANDERSON
Final 12/20/2023 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 12/20/2023 Approved DAVID ANDERSON
Service/Power Release 12/20/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 12/20/2023 Approved DAVID ANDERSON
Final 1/19/2024 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 1/19/2024 Not Ready for Inspection DAVID ANDERSON
Final 1/25/2024 Partial Approval DAVID ANDERSON
Service/Power Release 1/25/2024 Approved DAVID ANDERSON
Final 3/12/2024 Corrections Issued DAVID MATSON
Final 5/17/2024 OK to Issue CofO DAVID MATSON