121 N CRESCENT HEIGHTS BLVD 90048
Certificate Information: 121 N CRESCENT HEIGHTS BLVD 90048
- Application / Permit
- 22010-10000-01714
- Plan Check / Job No.
- B22LA06001
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Conversion of existing detached two-car garage into an Accessory Dwelling Unit (ADU) with addition per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2022 | GEORGE ALVAREZ |
| Corrections Issued | 4/8/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 5/21/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 6/4/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 8/27/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 8/31/2022 | GEORGE ALVAREZ |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 11/13/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/1/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 8/5/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shepphird,, William Reynolds; Lic. No.: C59229 | PO BOX 8446 CALABASAS, CA 91372 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/28/2023 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 4/28/2023 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 4/28/2023 | Approved | EVAN COOPER |
| METHANE-Subgrade | 4/28/2023 | Approved | EVAN COOPER |
| Green Building Rough | 6/8/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 6/8/2023 | Approved | JEREMY TODD |
| Underground Mechanical | 6/8/2023 | Approved | JEREMY TODD |
| Insulation | 7/6/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/6/2023 | Partial Approval | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/10/2023 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/13/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/13/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 7/13/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/13/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/13/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| Final | 11/2/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| Green Building Final | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| Final | 11/14/2023 | OK to Issue CofO | MEL KHACHATOURIAN |