1844 W 89TH ST 90047
Certificate Information: 1844 W 89TH ST 90047
- Application / Permit
- 22010-10000-01689
- Plan Check / Job No.
- B22LA05954
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT GARAGE TO 1 STORY ADU WITH ADDITION. "COMPLY WITH DEPARTMENT ORDER effective date 03/31/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Current Status
- Issued on 5/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 5/16/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 6/2/2022 | FARUK SEZER |
| Applicant returned to address corrections | 8/23/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/3/2024 | CRYSTEL MAALOUF |
| Issued | 5/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2022 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 2/23/2024 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2024 | DAVID VO |
| Roof/Waste drainage to street | Cleared | 3/1/2024 | DAVID VO |
| Sewer availability | Cleared | 3/1/2024 | DAVID VO |
Contact Information
| Contractor | Randle Construction; Lic. No.: 1002172-B | 13838 ROPER AVENUE NORWALK, CA 90650 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 9/3/2024 | Partial Approval | AMIR NAZARIAN |
| METHANE-Barrier | 9/3/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Subgrade | 9/3/2024 | Corrections Issued | AMIR NAZARIAN |
| Deputy Drilled-In Anchors | 2/27/2025 | Conditional Approval | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 3/3/2025 | Not Ready for Inspection | BARRY HACHE |
| METHANE-Rough | 3/3/2025 | Not Ready for Inspection | BARRY HACHE |
| METHANE-Rough | 3/18/2025 | Partial Inspection | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Not Ready for Inspection | JOSE MACIAS |
| Footing/Foundation/Slab | 4/7/2025 | Conditional Approval | JOSE MACIAS |
| METHANE-Barrier | 4/7/2025 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Subgrade | 4/7/2025 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/17/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Drywall Nailing | 4/17/2025 | Approved | WAYNE REGESTER |
| Footing/Foundation/Slab | 4/17/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Rough | 4/17/2025 | Approved | WAYNE REGESTER |
| Insulation | 4/17/2025 | Approved | WAYNE REGESTER |
| METHANE-Barrier | 4/17/2025 | Not Ready for Inspection | WAYNE REGESTER |
| METHANE-Rough | 4/17/2025 | Not Ready for Inspection | WAYNE REGESTER |
| METHANE-Subgrade | 4/17/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 6/4/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 6/4/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 6/4/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Final | 6/4/2025 | Approved | JOSE MACIAS |
| METHANE-Barrier | 6/4/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Final | 6/4/2025 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 6/4/2025 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 6/4/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 1/6/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |