12448 1/2 W GILMORE AVE 90066

Certificate Information: 12448 1/2 W GILMORE AVE 90066

Application / Permit
22010-10000-01684
Plan Check / Job No.
B22LA05942
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Storage conversion to accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP.
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/4/2022 MONICA RAMIREZ
Corrections Issued 4/5/2022 MONICA RAMIREZ
Plan Check Approved 4/19/2022 HELEN NGUYEN
Issued 4/28/2022 APPLICANT
CofO in Progress 6/21/2023 JESUS RODRIGUEZ
Permit Finaled 6/26/2023 DANIEL ORRANTE
CofO Issued 6/26/2023 DANIEL ORRANTE
Permit Finaled 6/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/9/2022 STEVEN JIN
Sewer availability Cleared 4/9/2022 STEVEN JIN
Specific Plan Cleared 4/12/2022 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 4/13/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/29/2022 Not Ready for Inspection JESUS RODRIGUEZ
Pre-Inspection 5/3/2022 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/5/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/17/2022 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/8/2022 Corrections Issued JESUS RODRIGUEZ
Pre-Inspection 6/8/2022 Partial Inspection RICHARD STEINBACH
Underground Mechanical 8/22/2022 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 8/23/2022 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 12/6/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 2/24/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 3/10/2023 Approved HERBERT GIRON
HVAC-Rough 3/10/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 3/10/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 3/16/2023 Approved HERBERT GIRON
PLUMBING-Rough 3/16/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/17/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 3/23/2023 Not Ready for Inspection BOBBY KEY
Green Building Rough 3/23/2023 Approved BOBBY KEY
Insulation 3/23/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 3/23/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 4/3/2023 Approved HERBERT GIRON
Drywall Nailing 4/3/2023 Approved HERBERT GIRON
Insulation 4/3/2023 Approved HERBERT GIRON
ELECTRICAL-Final 6/9/2023 Approved JESUS RODRIGUEZ
Final 6/9/2023 Conditional Approval JESUS RODRIGUEZ
Green Building Final 6/9/2023 Approved JESUS RODRIGUEZ
HVAC-Final 6/9/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/9/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 6/9/2023 Approved JESUS RODRIGUEZ
Final 6/20/2023 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 6/21/2023 Approved JESUS RODRIGUEZ