6848 N AMIGO AVE 91335

Certificate Information: 6848 N AMIGO AVE 91335

Application / Permit
22010-10000-01681
Plan Check / Job No.
B22LA05929
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 10/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 DANIEL YIP
Corrections Issued 4/18/2022 DANIEL YIP
Quality Review Completed 4/20/2022 KEN GILL
Building Plans Picked Up 4/25/2022 APPLICANT
Plan Check Approved 9/26/2022 DANIEL YIP
Plan Check Approved 9/26/2022 DANIEL YIP
Issued 10/5/2022 APPLICANT
CofO in Progress 12/12/2024 ARUTYUN MADATYAN
Permit Finaled 1/3/2025 JOHN JANSON
CofO Issued 1/3/2025 JOHN JANSON
Permit Finaled 1/3/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/12/2022 CARLOS AGUILERA
Permit Cleared 5/12/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/13/2022 CARLOS AGUILERA
Sewer availability Cleared 5/13/2022 CARLOS AGUILERA
Low Impact Development Cleared 9/14/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/16/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/22/2022 Approved JEFFREY BULL
Excavation/Setback/Form/Re-Bar 12/1/2022 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Approved JEFFREY BULL
Underground Mechanical 3/9/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 3/20/2023 Approved VINCENT HANLEY
HVAC-Rough 3/20/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 3/20/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/29/2023 Approved JEFFREY BULL
HVAC-Rough 3/29/2023 Approved JEFFREY BULL
PLUMBING-Rough 3/29/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 4/10/2023 Approved SEAN WIRCH
Green Building Rough 4/10/2023 Approved SEAN WIRCH
Insulation 4/10/2023 Approved SEAN WIRCH
Verify Sprinkler Sign Off 4/10/2023 Approved SEAN WIRCH
Drywall Nailing 4/14/2023 Approved JUSTIN HAWLEY
Shower Pan 6/15/2023 Approved JEFFREY BULL
Final 7/26/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 7/26/2024 Approved JEFFREY BULL
Green Building Final 7/26/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 7/26/2024 Approved JEFFREY BULL
Smoke Detectors 7/26/2024 Approved JEFFREY BULL
ELECTRICAL-Final 11/15/2024 Approved ARUTYUN MADATYAN
Final 11/15/2024 Conditional Approval ARUTYUN MADATYAN
Green Building Final 11/15/2024 Approved ARUTYUN MADATYAN
HVAC-Final 11/15/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 11/15/2024 Approved ARUTYUN MADATYAN
Final 12/11/2024 OK to Issue CofO ARUTYUN MADATYAN