6416 S DENVER AVE 90044
Certificate Information: 6416 S DENVER AVE 90044
- Application / Permit
- 22010-10000-01676
- Plan Check / Job No.
- B22LA05917
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT PER ORDINANCE LAMC12.22A.33(b)(1) WITH ATTACHED 4-CAR GARAGE AT THE REAR OF LOT
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | VU NGUYEN |
| Corrections Issued | 4/19/2022 | VU NGUYEN |
| Quality Review Completed | 4/21/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| Plan Check Approved | 6/30/2022 | VU NGUYEN |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 1/17/2023 | LILIANA PORTILLO |
| Permit Finaled | 1/25/2023 | DEROLD HAUFF |
| CofO Issued | 1/25/2023 | DEROLD HAUFF |
| Permit Finaled | 1/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 5/11/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 6/8/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 6/20/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/21/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/25/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/30/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/30/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 10/19/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/19/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 10/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 10/24/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/28/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 11/22/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 11/22/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/29/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/11/2023 | Approved | LILIANA PORTILLO |
| Green Building Final | 1/11/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/11/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/11/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 1/11/2023 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 1/11/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/12/2023 | Approved | LILIANA PORTILLO |
| Final | 1/12/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 1/12/2023 | Approved | LILIANA PORTILLO |
| MERV13>=Final | 1/12/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | LILIANA PORTILLO |
| Final | 1/13/2023 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 1/13/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 1/13/2023 | Approved | LILIANA PORTILLO |
| MERV13>=Final | 1/13/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/13/2023 | Approved | LILIANA PORTILLO |