467 S DALEHURST AVE 90024
Certificate Information: 467 S DALEHURST AVE 90024
- Application / Permit
- 22010-10000-01651
- Plan Check / Job No.
- B22LA05844
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY OVER BASEMENT SINGLE FAMILY DWELLING WITH ATTACHED 6-CAR GARAGE
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- Metro
- Current Status
- Issued on 6/12/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 4/26/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 4/27/2022 | PETER KIM |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Applicant returned to address corrections | 6/3/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 6/24/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/10/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/18/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/2/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/11/2023 | ARMEN JIVALAGIAN |
| Plan Check Approved | 5/30/2023 | ARMEN JIVALAGIAN |
| Issued | 6/12/2023 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 7/25/2022 | DALIA MOKAYED |
| Specific Plan | Cleared | 8/1/2022 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 9/25/2022 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 10/18/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/28/2022 | LUIS LUVANO |
| Miscellaneous | Cleared | 11/8/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 11/9/2022 | JENSON LEE |
| Address approval | Cleared | 12/5/2022 | JENSON LEE |
| Permit | Cleared | 12/7/2022 | JENSON LEE |
| Sewer availability | Cleared | 12/7/2022 | JENSON LEE |
| Excavation more than 5-ft deep | Cleared | 1/10/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/10/2023 | ARMEN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 1/10/2023 | ARMEN JIVALAGIAN |
Contact Information
| Contractor | Elite Remodeling & Construction Inc; Lic. No.: 823311-B | 6351 WILSHIRE BLVD STE 101 LOS ANGELES, CA 90048 |
| Engineer | Gaprelian,, Armen; Lic. No.: GE2668 | 1719 BEN LOMOND DR GLENDALE, CA 91202 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/13/2023 | Partial Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/24/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/16/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Underground Mechanical | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 10/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 10/31/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/31/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/20/2023 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 2/16/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/4/2024 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 3/7/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/7/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/12/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 3/13/2024 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 3/14/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 5/2/2024 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 5/16/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 5/17/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Steel/Welding | 5/20/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 5/30/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 6/24/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/24/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 6/25/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 6/26/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 7/1/2024 | Partial Approval | SEAN HAUPT |
| Reinforced Concrete Frame | 7/1/2024 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 7/3/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/9/2024 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/5/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Inspection | 9/17/2024 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 9/24/2024 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 10/15/2024 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 10/22/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 10/30/2024 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 11/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 11/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 11/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 11/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/20/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 12/2/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 12/2/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/13/2025 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/8/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 4/8/2025 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 4/8/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 4/10/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 4/10/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 4/15/2025 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/22/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/22/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 4/22/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Sewer | 5/12/2025 | Not Ready for Inspection | DANIEL VERA |
| Sewer | 5/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Underground Mechanical | 5/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Sewer | 5/15/2025 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 5/15/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/5/2025 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | DANIEL VERA |
| Green Building Rough | 6/16/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 6/16/2025 | Approved | DANIEL VERA |
| Insulation | 6/23/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 7/8/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 3/9/2026 | Corrections Issued | RYAN SALAZAR |
| Gas Test | 3/9/2026 | Approved | RYAN SALAZAR |
| HVAC-Final | 3/9/2026 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Final | 3/9/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 5/13/2026 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/13/2026 | Approved | DAVID SCANTLIN |
| Green Building Final | 5/13/2026 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/13/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 5/13/2026 | Approved | DAVID SCANTLIN |