8301 N VALJEAN AVE 91343

Certificate Information: 8301 N VALJEAN AVE 91343

Application / Permit
22010-10000-01645
Plan Check / Job No.
B22LA05813
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
BUILDING PERMIT FOR NEW REC. ROOM 1 OF 3
Permit Issued
Issued on 9/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ADRIANA LOPEZ
Corrections Issued 5/11/2022 ADRIANA LOPEZ
Quality Review Completed 5/13/2022 FARUK SEZER
Building Plans Picked Up 5/17/2022 APPLICANT
Plan Check Approved 9/14/2022 ADRIANA LOPEZ
Issued 9/16/2022 APPLICANT
CofO in Progress 3/4/2024 RAUL OLAGI
Permit Finaled 4/1/2024 RONALD MYRICK
CofO Issued 4/1/2024 RONALD MYRICK
Permit Finaled 4/1/2024 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/3/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/10/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 8/17/2022 DAGOVERTO GUERRERO
Private sewage disp. approval Cleared 8/29/2022 ADRIANA LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 10/18/2022 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 10/18/2022 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/24/2022 Partial Approval RAUL OLAGI
Deputy Reinf. Concrete 10/26/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 11/2/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/17/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/17/2023 Corrections Issued RAUL OLAGI
Green Building Rough 2/17/2023 Approved RAUL OLAGI
HVAC-Rough 2/17/2023 Approved RAUL OLAGI
PLUMBING-Rough 2/17/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 2/17/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/6/2023 Approved RAUL OLAGI
Insulation 3/6/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 3/6/2023 Approved RAUL OLAGI
Drywall Nailing 3/17/2023 Approved RAUL OLAGI
Underground Mechanical 5/10/2023 Partial Approval JUAN VALENZUELA
ELECTRICAL-Final 10/11/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Final 10/11/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Final 10/11/2023 Not Ready for Inspection RAUL OLAGI
Final 11/20/2023 Corrections Issued RAUL OLAGI
Green Building Final 11/20/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved RAUL OLAGI
Service/Power Release 11/20/2023 Approved RAUL OLAGI
Smoke Detectors 11/20/2023 Approved RAUL OLAGI
ELECTRICAL-Final 1/9/2024 No Access for Inspection RAUL OLAGI
Final 1/9/2024 No Access for Inspection RAUL OLAGI
HVAC-Final 1/9/2024 No Access for Inspection RAUL OLAGI
PLUMBING-Final 1/9/2024 No Access for Inspection RAUL OLAGI
ELECTRICAL-Final 1/11/2024 Approved RAUL OLAGI
Final 1/11/2024 Corrections Issued RAUL OLAGI
HVAC-Final 1/11/2024 Approved RAUL OLAGI
PLUMBING-Final 1/11/2024 Approved RAUL OLAGI
Final 3/4/2024 OK to Issue CofO RAUL OLAGI