12834 W GILMORE AVE 90066

Certificate Information: 12834 W GILMORE AVE 90066

Application / Permit
22010-10000-01639
Plan Check / Job No.
B22LA05788
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 5/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/11/2022 JAD BASMA
Corrections Issued 4/11/2022 JAD BASMA
Building Plans Picked Up 4/12/2022 APPLICANT
Plan Check Approved 5/6/2022 RICARDO RAMIREZ
Issued 5/6/2022 APPLICANT
CofO in Progress 12/8/2022 HERBERT GIRON
Permit Finaled 12/19/2022 DANIEL ORRANTE
CofO Issued 12/19/2022 DANIEL ORRANTE
Permit Finaled 12/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/19/2022 CATHERINE ADROVER
Address approval Cleared 4/19/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 4/20/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 4/20/2022 CATHERINE ADROVER
Sewer availability Cleared 4/20/2022 CATHERINE ADROVER

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107
Geologist Siskowic,, John Gary; Lic. No.: GEO8255 515 S CATALINA AVE APT A      REDONDO BEACH, CA 90277

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2022 Approved JESUS RODRIGUEZ
METHANE-Barrier 5/19/2022 Approved JESUS RODRIGUEZ
METHANE-Subgrade 5/19/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/6/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Conditional Approval JESUS RODRIGUEZ
HVAC-Rough 7/6/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/6/2022 Approved JESUS RODRIGUEZ
Shower Pan 7/19/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 7/25/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 7/29/2022 Partial Approval HERBERT GIRON
Green Building Rough 7/29/2022 Approved HERBERT GIRON
Insulation 7/29/2022 Corrections Issued HERBERT GIRON
Insulation 8/4/2022 Approved HERBERT GIRON
Drywall Nailing 8/11/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/11/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 11/2/2022 Partial Approval HERBERT GIRON
ELECTRICAL-Final 11/2/2022 Not Ready for Inspection HERBERT GIRON
Final 11/2/2022 Corrections Issued HERBERT GIRON
Green Building Final 11/2/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Final 11/2/2022 Corrections Issued HERBERT GIRON
METHANE-Final 11/2/2022 Approved HERBERT GIRON
METHANE-Rough 11/2/2022 Approved HERBERT GIRON
PLUMBING-Final 11/2/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Approved HERBERT GIRON
Service/Power Release 11/2/2022 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 11/2/2022 Corrections Issued HERBERT GIRON
Verify Sprinkler Sign Off 11/2/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/21/2022 Corrections Issued HERBERT GIRON
HVAC-Final 11/21/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/21/2022 Corrections Issued HERBERT GIRON
HVAC-Final 11/30/2022 Approved HERBERT GIRON
PLUMBING-Final 11/30/2022 Approved HERBERT GIRON
ELECTRICAL-Final 12/2/2022 Conditional Approval HERBERT GIRON
Service/Power Release 12/2/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 12/7/2022 Approved HERBERT GIRON
ELECTRICAL-Final 12/7/2022 Approved HERBERT GIRON
Final 12/7/2022 OK to Issue CofO HERBERT GIRON
Green Building Final 12/7/2022 Approved HERBERT GIRON
Service/Power Release 12/7/2022 Not Required HERBERT GIRON
Smoke Detectors 12/7/2022 Approved HERBERT GIRON