12834 W GILMORE AVE 90066
Certificate Information: 12834 W GILMORE AVE 90066
- Application / Permit
- 22010-10000-01639
- Plan Check / Job No.
- B22LA05788
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2022 | JAD BASMA |
| Corrections Issued | 4/11/2022 | JAD BASMA |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Plan Check Approved | 5/6/2022 | RICARDO RAMIREZ |
| Issued | 5/6/2022 | APPLICANT |
| CofO in Progress | 12/8/2022 | HERBERT GIRON |
| Permit Finaled | 12/19/2022 | DANIEL ORRANTE |
| CofO Issued | 12/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2022 | CATHERINE ADROVER |
| Address approval | Cleared | 4/19/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 4/20/2022 | CATHERINE ADROVER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
| Geologist | Siskowic,, John Gary; Lic. No.: GEO8255 | 515 S CATALINA AVE APT A REDONDO BEACH, CA 90277 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| METHANE-Barrier | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| METHANE-Subgrade | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/6/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 7/6/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/6/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 7/19/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 7/25/2022 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/29/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 7/29/2022 | Approved | HERBERT GIRON |
| Insulation | 7/29/2022 | Corrections Issued | HERBERT GIRON |
| Insulation | 8/4/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/11/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/11/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/2/2022 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Final | 11/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| METHANE-Final | 11/2/2022 | Approved | HERBERT GIRON |
| METHANE-Rough | 11/2/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 11/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 11/2/2022 | Corrections Issued | HERBERT GIRON |
| Verify Sprinkler Sign Off | 11/2/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/21/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/30/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/30/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/2/2022 | Conditional Approval | HERBERT GIRON |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/7/2022 | Approved | HERBERT GIRON |
| Final | 12/7/2022 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 12/7/2022 | Approved | HERBERT GIRON |
| Service/Power Release | 12/7/2022 | Not Required | HERBERT GIRON |
| Smoke Detectors | 12/7/2022 | Approved | HERBERT GIRON |