1605 N REDESDALE AVE 90026
Certificate Information: 1605 N REDESDALE AVE 90026
- Application / Permit
- 22010-10000-01611
- Plan Check / Job No.
- B22LA05672
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW PERGOLA
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Metro
- Current Status
- Issued on 3/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | JAD BASMA |
| Corrections Issued | 5/13/2022 | JAD BASMA |
| Quality Review Completed | 5/24/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Applicant returned to address corrections | 8/25/2022 | JAD BASMA |
| Plan Check Approved | 9/26/2022 | JAD BASMA |
| Issued | 3/10/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/26/2022 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 5/10/2023 | Partial Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Other (see comments) | 7/7/2023 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Other (see comments) | 9/18/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/5/2023 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/20/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 11/27/2023 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/3/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 10/3/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/3/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/3/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/3/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/6/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 11/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 12/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/6/2024 | Approved | HAMIK HARTOUNIAN |