531 N EDINBURGH AVE 90048

Certificate Information: 531 N EDINBURGH AVE 90048

Application / Permit
22010-10000-01606
Plan Check / Job No.
B22LA05630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (ZC: 628 SF) DETACHED ADU (42' X 19'-2") PER LAMC 12.22A.33(c)-(d). PV SYSTEM TO BE INSTALLED UNDER SEPARATE PERMIT ON MAIN DWELLING TO BACK FEED TO ADU PRIOR TO C OF O OF ADU.
Permit Issued
Issued on 8/16/2022
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2022 APPLICANT
Assigned to Plan Check Engineer 4/5/2022 VIVIAN LAO
Corrections Issued 4/5/2022 VIVIAN LAO
Applicant returned to address corrections 5/27/2022 VIVIAN LAO
Plan Check Approved 7/29/2022 JOE VO
Issued 8/16/2022 APPLICANT
CofO in Progress 9/12/2023 LILIANA PORTILLO
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction within easement Cleared 4/21/2022 TINA MIRANDA
Address approval Cleared 5/26/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 6/7/2022 AMAAN MALIK
Sewer availability Cleared 6/7/2022 AMAAN MALIK
Low Impact Development Cleared 7/22/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 7/23/2022 JEANETTE VONG

Contact Information

Contractor Castillo Construction; Lic. No.: 960211-B 228 GRAND BOULEVARD      VENICE, CA 90291
Engineer Garza,, Omar Leonel; Lic. No.: NA5593       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2022 Approved MICHAEL LEWIS
METHANE-Barrier 10/25/2022 Approved MICHAEL LEWIS
METHANE-Subgrade 10/25/2022 Approved MICHAEL LEWIS
Underground Mechanical 10/25/2022 Approved MICHAEL LEWIS
Footing/Foundation/Slab 11/4/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 12/22/2022 Approved MICHAEL LEWIS
HVAC-Rough 12/22/2022 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 12/22/2022 Partial Approval MICHAEL LEWIS
HVAC-Rough 12/28/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 12/28/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/29/2022 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval MICHAEL LEWIS
Underground Mechanical 12/29/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Approved MICHAEL LEWIS
Green Building Rough 1/17/2023 Approved MICHAEL LEWIS
Insulation 1/17/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/17/2023 Approved MICHAEL LEWIS
Shower Pan 1/17/2023 Not Ready for Inspection MICHAEL LEWIS
Drywall Nailing 1/23/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/23/2023 Approved MICHAEL LEWIS
Shower Pan 1/23/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 2/21/2023 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 8/15/2023 Conditional Approval LILIANA PORTILLO
Final 8/15/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 8/15/2023 Corrections Issued LILIANA PORTILLO
METHANE-Final 8/15/2023 Approved LILIANA PORTILLO
METHANE-Rough 8/15/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 8/15/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 8/15/2023 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 8/15/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/31/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/31/2023 Approved LILIANA PORTILLO
Final 8/31/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 8/31/2023 Approved LILIANA PORTILLO
HVAC-Final 8/31/2023 Approved LILIANA PORTILLO
PLUMBING-Final 8/31/2023 Approved LILIANA PORTILLO
Service/Power Release 8/31/2023 Not Ready for Inspection LILIANA PORTILLO
Final 9/11/2023 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 9/11/2023 Approved LILIANA PORTILLO