2825 E MICHIGAN AVE 90033
Certificate Information: 2825 E MICHIGAN AVE 90033
- Application / Permit
- 22010-10000-01604
- Plan Check / Job No.
- B22LA05626
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 1 STORY ADU
- Permit Issued
- Issued on 10/22/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 5/16/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 6/2/2022 | FARUK SEZER |
| Applicant returned to address corrections | 6/30/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/2/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/12/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/19/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/21/2022 | CRYSTEL MAALOUF |
| Issued | 10/22/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | FREDDIE RIVERA |
| No Progress | 3/22/2024 | FREDDIE RIVERA |
| CofO in Progress | 3/22/2024 | FREDDIE RIVERA |
| Permit Finaled | 4/11/2024 | DEROLD HAUFF |
| Permit Finaled | 4/11/2024 | DEROLD HAUFF |
| CofO Issued | 4/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/31/2022 | KIRK LINKLATER |
| Address approval | Cleared | 6/1/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/14/2022 | AMAAN MALIK |
Contact Information
| Contractor | Carolina Nazario; Lic. No.: 1072428-B | , |
| Contractor | Mr Design & Build; Lic. No.: 1072428-B | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/28/2022 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 11/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Deputy Methane Barrier | 11/21/2022 | No Result Entered | ROBERT VORHIS |
| METHANE-Rough | 11/29/2022 | Partial Approval | FREDDIE RIVERA |
| Deputy Methane Barrier | 12/8/2022 | Partial Approval | JEFFREY MEAD |
| Deputy Methane Barrier | 12/15/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/15/2022 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 12/15/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 12/15/2022 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/21/2022 | Approved | BRENDAN MORELLI |
| METHANE-Barrier | 12/21/2022 | Approved | BRENDAN MORELLI |
| METHANE-Subgrade | 12/21/2022 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/19/2023 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Rough | 1/19/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/19/2023 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/19/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/23/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/23/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/2/2023 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 2/14/2023 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/21/2023 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 2/21/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/22/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/22/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/8/2023 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Rough | 3/8/2023 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 3/14/2023 | Conditional Approval | BRENDAN MORELLI |
| Drywall Nailing | 3/22/2023 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 7/13/2023 | Partial Inspection | FREDDIE RIVERA |
| Underground Mechanical | 7/13/2023 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Final | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 9/11/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 9/13/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/13/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/13/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/21/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 9/21/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Final | 9/21/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 9/21/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 9/21/2023 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 9/21/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/6/2023 | Approved | FREDDIE RIVERA |
| Final | 10/6/2023 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 10/6/2023 | Approved | FREDDIE RIVERA |
| METHANE-Final | 10/6/2023 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 10/6/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 10/6/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/6/2023 | Approved | FREDDIE RIVERA |
| Final | 11/6/2023 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 11/6/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 11/6/2023 | Approved | FREDDIE RIVERA |
| Final | 11/20/2023 | Conditional Approval | FREDDIE RIVERA |
| Final | 11/29/2023 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 11/29/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/8/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 4/8/2024 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 4/8/2024 | Partial Inspection | FREDDIE RIVERA |