1043 W 65TH ST 90047

Certificate Information: 1043 W 65TH ST 90047

Application / Permit
22010-10000-01583
Plan Check / Job No.
B22LA05542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) garage to ADU and addition for ADU.
Permit Issued
Issued on 8/25/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 FERNANDO FLORES
Corrections Issued 4/9/2022 FERNANDO FLORES
Applicant returned to address corrections 6/2/2022 RAHEL BEYENE
Plan Check Approved 8/25/2022 SAMUEL GONZALEZ
Issued 8/25/2022 APPLICANT
CofO in Progress 4/8/2024 RONNIE MINDANAO
Permit Finaled 4/12/2024 DEROLD HAUFF
Permit Finaled 4/12/2024 DEROLD HAUFF
CofO Issued 4/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/20/2022 AMAAN MALIK
Sewer availability Cleared 5/20/2022 AMAAN MALIK
Low Impact Development Cleared 6/2/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 6/3/2022 AMAAN MALIK
Construction near power lines Cleared 8/20/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/30/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/6/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/7/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/7/2022 Approved ENRIQUE MIRELES
Drywall Nailing 2/16/2023 Approved ENRIQUE MIRELES
Green Building Rough 2/16/2023 Approved ENRIQUE MIRELES
Wood Frame 6/5/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/21/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/21/2023 Approved ENRIQUE MIRELES
Final 12/21/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 12/21/2023 Approved ENRIQUE MIRELES
HVAC-Final 12/21/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 12/21/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/21/2023 Approved ENRIQUE MIRELES
Final 2/14/2024 Corrections Issued RONNIE MINDANAO
Final 2/26/2024 Conditional Approval RONNIE MINDANAO
Final 4/8/2024 OK to Issue CofO RONNIE MINDANAO