1043 W 65TH ST 90047
Certificate Information: 1043 W 65TH ST 90047
- Application / Permit
- 22010-10000-01583
- Plan Check / Job No.
- B22LA05542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) garage to ADU and addition for ADU.
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | FERNANDO FLORES |
| Corrections Issued | 4/9/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/2/2022 | RAHEL BEYENE |
| Plan Check Approved | 8/25/2022 | SAMUEL GONZALEZ |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 4/8/2024 | RONNIE MINDANAO |
| Permit Finaled | 4/12/2024 | DEROLD HAUFF |
| Permit Finaled | 4/12/2024 | DEROLD HAUFF |
| CofO Issued | 4/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/20/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 6/2/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 6/3/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 8/20/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/6/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/7/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/7/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 2/16/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 2/16/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/5/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/21/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 12/21/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 12/21/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 12/21/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/14/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 2/26/2024 | Conditional Approval | RONNIE MINDANAO |
| Final | 4/8/2024 | OK to Issue CofO | RONNIE MINDANAO |