1535 1/2 W DUANE ST 90026

Certificate Information: 1535 1/2 W DUANE ST 90026

Application / Permit
22010-10000-01573
Plan Check / Job No.
B22LA05480
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1 STORY DETACHED ADU 1 OF 3
Permit Issued
Issued on 7/17/2023
Issuing Office
Metro
Current Status
Issued on 7/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/31/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 ARSALAN SHABESTARI
Corrections Issued 4/28/2022 ARSALAN SHABESTARI
Quality Review Completed 5/2/2022 KEN GILL
Building Plans Picked Up 5/13/2022 APPLICANT
Applicant returned to address corrections 2/8/2023 ARSALAN SHABESTARI
Plan Check Approved 5/5/2023 ARSALAN SHABESTARI
Issued 7/17/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/29/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/29/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/29/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/29/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/29/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 9/8/2022 KIRK LINKLATER
BHO/Hillside ordinance Cleared 9/20/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/26/2022 STEVE MELGAR
Sewer availability Cleared 9/26/2022 STEVE MELGAR
Low Impact Development Cleared 10/21/2022 SARAH YOUSSEF
Hydrant and Access approval Cleared 12/1/2022 KURT CORRAL
Roof/Waste drainage to street Cleared 12/7/2022 STEVE MELGAR
GPI Written Notices Cleared 2/8/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/22/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 3/28/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 4/1/2024 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 4/18/2024 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/6/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/6/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/28/2024 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval SCOTT FINNILA
Underground Mechanical 6/28/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 10/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 10/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved HAMIK HARTOUNIAN
Green Building Rough 11/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 11/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/14/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 4/25/2025 Corrections Issued HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 4/25/2025 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/28/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 4/28/2025 Approved HAMIK HARTOUNIAN
Shower Pan 4/28/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/8/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 5/8/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 5/8/2025 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 5/8/2025 Corrections Issued HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 5/8/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/19/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 5/19/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/19/2025 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 5/19/2025 Approved HAMIK HARTOUNIAN
Insulation 5/21/2025 Corrections Issued HAMIK HARTOUNIAN
Insulation 5/27/2025 Approved ALEX COLIN
Drywall Nailing 6/6/2025 Approved ALEX COLIN
Final 11/17/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/17/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV No Gas HAMIK HARTOUNIAN
Service/Power Release 11/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 11/17/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 3/18/2026 Corrections Issued HAMIK HARTOUNIAN