2254 E 97TH ST 1-14 90002
Certificate Information: 2254 E 97TH ST 1-14 90002
- Application / Permit
- 22010-10000-01553
- Plan Check / Job No.
- B22LA05421
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN. New 2-story 14 unit housing apartment to include 2-story type VA apartment
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | KEVIN MORALES |
| Corrections Issued | 5/16/2022 | KEVIN MORALES |
| Quality Review Completed | 5/18/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/31/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 9/7/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 2/22/2023 | KEVIN MORALES |
| Plan Check Approved | 7/13/2023 | KEVIN MORALES |
| Issued | 8/16/2023 | APPLICANT |
| TCO Issued (Expire Date: 03-04-2026) | 9/5/2025 | ERNESTO CORRAL |
| CofO in Progress | 1/16/2026 | JAMES POWERS |
| Permit Finaled | 1/16/2026 | ERNESTO CORRAL |
| Permit Finaled | 1/16/2026 | ERNESTO CORRAL |
| CofO Issued | 1/16/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 5/24/2022 | KEVIN MORALES |
| Frnt yard landscape/Water mgmt | Cleared | 7/15/2022 | JASON CHAN |
| Miscellaneous | Cleared | 7/15/2022 | JASON CHAN |
| Opn space landscape/Water mgmt | Cleared | 7/15/2022 | JASON CHAN |
| Tract Map conditions | Cleared | 7/15/2022 | JASON CHAN |
| Tract Map conditions | Cleared | 7/15/2022 | JASON CHAN |
| ZA Case | Cleared | 7/15/2022 | JASON CHAN |
| ZA Case | Cleared | 7/15/2022 | JASON CHAN |
| ZA Case | Cleared | 7/15/2022 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | TREVOR QUAN |
| Green Code | Cleared | 9/15/2022 | AARON COSTA |
| Trees in Parkway | Cleared | 1/12/2023 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 1/18/2023 | RICHARD SANCHEZ |
| Low Impact Development | Cleared | 2/13/2023 | AMMAR ELTAWIL |
| Address approval | Cleared | 3/2/2023 | STEVE MELGAR |
| Permit | Cleared | 3/3/2023 | TERRY PHAN |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | TERRY PHAN |
| Highway dedication | Cleared | 3/7/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/16/2023 | KURT CORRAL |
| Sewer availability | Cleared | 3/16/2023 | STEVE MELGAR |
| Work Adjacent to Public Way | Cleared | 5/22/2023 | KEVIN MORALES |
| Public Housing | Cleared | 5/25/2023 | GUS VINDELL |
| DAS Clearance | Cleared | 5/26/2023 | OLLIE CARTER |
| Specific Plan | Cleared | 6/9/2023 | DAISY BENICIA |
| Density Bonus | Cleared | 7/12/2023 | JAMES MCCARTHY |
| SB8 RUD | Cleared | 7/12/2023 | JAMES MCCARTHY |
| Building over 36-ft | Cleared | 7/13/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Portrait Construction Inc; Lic. No.: 977636-B | 265 N JOY STREET #200 CORONA, CA 92879 |
| Engineer | Aden,, Mark D; Lic. No.: S4779 | 1314 S GRAND BLVD 2-359 SPOKANE, WA 99202 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2024 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 4/26/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/23/2024 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/28/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/17/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 6/17/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/1/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/1/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 7/3/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 8/2/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/2/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 8/2/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Partial Approval | JAMES POWERS |
| Insulation | 8/21/2024 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 8/23/2024 | Approved | JAMES POWERS |
| Insulation | 8/23/2024 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/23/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 8/23/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 8/27/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/29/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Partial Approval | JAMES POWERS |
| Insulation | 9/10/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 10/4/2024 | Approved | JAMES POWERS |
| Light Gage Steel Frame | 10/7/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Partial Inspection | RONALD JIMENEZ |
| Insulation | 10/11/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Verify Sprinkler Sign Off | 10/11/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 10/11/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Partial Approval | LARRY ARNICK |
| Insulation | 10/15/2024 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Wood Construction | 10/17/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 10/21/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 6/27/2025 | Approved | JAMES POWERS |
| Final | 6/27/2025 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 6/27/2025 | Approved | JAMES POWERS |
| Green Building Final | 6/27/2025 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 6/27/2025 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/27/2025 | Approved | JAMES POWERS |
| Wood Frame | 6/27/2025 | Approved | JAMES POWERS |
| Final | 7/9/2025 | Not Ready for Inspection | JAMES POWERS |
| Smoke Detectors | 7/9/2025 | Approved | JAMES POWERS |
| Final | 8/21/2025 | OK for TCO | JAMES POWERS |
| Deputy Steel/Welding | 1/15/2026 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 1/16/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/16/2026 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 1/16/2026 | Partial Approval | JAMES POWERS |
| Final | 1/16/2026 | OK to Issue CofO | JAMES POWERS |