3893 S 3RD AVE 90008
Certificate Information: 3893 S 3RD AVE 90008
- Application / Permit
- 22010-10000-01528
- Plan Check / Job No.
- B22LA05322
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Construct new detached accessory dwelling unit per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Current Status
- CofO Issued on 1/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | VU NGUYEN |
| Corrections Issued | 4/12/2022 | VU NGUYEN |
| Quality Review Completed | 4/15/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/12/2022 | VU NGUYEN |
| Applicant returned to address corrections | 5/20/2022 | VU NGUYEN |
| Plan Check Approved | 6/8/2022 | VU NGUYEN |
| Issued | 7/20/2022 | APPLICANT |
| CofO in Progress | 1/4/2024 | ANTHONY EGSON |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| CofO Issued | 1/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/16/2022 | PATRICK MAGALLANES |
| Address approval | Cleared | 4/18/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | CELINA MORENO |
| Sewer availability | Cleared | 4/20/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/27/2022 | CELINA MORENO |
Contact Information
| Contractor | E G N Builders Group; Lic. No.: 1051430-B | 24007 VENTURA BLVD STE 102 CALABASAS, CA 91302 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/26/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 7/29/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/5/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/10/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/20/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 9/20/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 9/20/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/26/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 9/26/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Approved | ANTHONY EGSON |
| Gas Test | 9/30/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 9/30/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/11/2022 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/20/2022 | Approved | ANTHONY EGSON |
| Insulation | 10/27/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 11/1/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 11/10/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/30/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 11/30/2022 | Partial Approval | ANTHONY EGSON |
| Sewer | 12/7/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/7/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/30/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/30/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 1/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 1/30/2023 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 1/30/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 1/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 1/30/2023 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 1/30/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/8/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 3/8/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 3/8/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/8/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/13/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 3/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 3/13/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 3/13/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 3/22/2023 | Approved | ANTHONY EGSON |
| Final | 3/22/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 10/5/2023 | No Access for Inspection | ANTHONY EGSON |
| Service/Power Release | 10/5/2023 | No Access for Inspection | ANTHONY EGSON |
| Final | 10/11/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 12/15/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 1/3/2024 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 1/3/2024 | Approved | ANTHONY EGSON |