6304 S 7TH AVE 90043
Certificate Information: 6304 S 7TH AVE 90043
- Application / Permit
- 22010-10000-01496
- Plan Check / Job No.
- B22LA05155
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 BEDROOM, 896 SQ FT DETACHED ADU @ REAR OF PROPERTY
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 4/29/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| Plan Check Approved | 3/31/2023 | MARCELA FRANQUEZ |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 1/4/2024 | ENRIQUE MIRELES |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| CofO Issued | 1/13/2024 | DEROLD HAUFF |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction within easement | Cleared | 11/15/2022 | TINA MIRANDA |
| Address approval | Cleared | 1/3/2023 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/4/2023 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 3/6/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/24/2023 | AMAAN MALIK |
Contact Information
| Contractor | Glenford Construction; Lic. No.: 950038-B | 1436 7TH STREET #U RIVERSIDE, CA 92507 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/17/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/17/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/17/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/17/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/17/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/17/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/31/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/31/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/1/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 8/1/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/24/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 8/24/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/1/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 9/1/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/12/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 10/16/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/21/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/21/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/21/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 11/28/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 11/30/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/29/2023 | OK to Issue CofO | ENRIQUE MIRELES |