15149 W MORRISON ST 91403

Certificate Information: 15149 W MORRISON ST 91403

Application / Permit
22010-10000-01491
Plan Check / Job No.
B22LA05146
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached Accessory Dwelling Unit and patio cover per CA GC 65852.2(E)(1)(B). LID DEFERRED SUBMITTAL
Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 CARLOS MONTES
Corrections Issued 4/2/2022 CARLOS MONTES
Quality Review Completed 4/4/2022 LIPING TENG
Plan Check Approved 5/12/2022 CARLOS MONTES
Issued 5/12/2022 APPLICANT
CofO in Progress 12/19/2023 THOMAS FINNILA
Permit Finaled 1/17/2024 RUBEN SALAS
CofO Issued 1/17/2024 RUBEN SALAS
Permit Finaled 1/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/2/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/2/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/4/2022 CARLOS AGUILERA
Sewer availability Cleared 4/4/2022 CARLOS AGUILERA
ZI Cleared 4/11/2022 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,
Engineer Wassef,, Mena; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/28/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 6/28/2022 Not Ready for Inspection JOHN HAYES
Sewer 6/28/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 7/5/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 7/5/2022 Partial Approval JACK KARGODORIAN
Sewer 7/5/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 8/16/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 8/16/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 8/16/2022 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 8/16/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/16/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/16/2022 Approved CHRISTOPHE COCHRAN
Insulation 8/23/2022 Not Ready for Inspection CALEB MEISTER
Wood Frame 8/23/2022 Not Ready for Inspection CALEB MEISTER
Insulation 9/7/2022 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 9/7/2022 Approved JACK KARGODORIAN
Insulation 9/20/2022 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 10/18/2022 Corrections Issued THOMAS FINNILA
Drywall Nailing 10/27/2022 Approved CALEB MEISTER
Service/Power Release 5/2/2023 No Access for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/26/2023 Approved THOMAS FINNILA
Final 5/26/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 5/26/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready THOMAS FINNILA
Final 12/1/2023 Corrections Issued THOMAS FINNILA
Green Building Final 12/1/2023 Approved THOMAS FINNILA
MERV13>=Final 12/1/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 12/1/2023 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 12/1/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 12/7/2023 Approved THOMAS FINNILA
Final 12/12/2023 Partial Approval THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Approved THOMAS FINNILA
Service/Power Release 12/12/2023 Approved THOMAS FINNILA
Final 12/18/2023 OK to Issue CofO THOMAS FINNILA