5318 E ALDAMA ST 90042

Certificate Information: 5318 E ALDAMA ST 90042

Application / Permit
22010-10000-01489
Plan Check / Job No.
B22LA05143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 1/4/2024
Issuing Office
Current Status
Issued on 1/4/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/31/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 MONICA RAMIREZ
Corrections Issued 5/9/2022 MONICA RAMIREZ
Quality Review Completed 5/11/2022 RODOLFO ARIAS
Applicant returned to address corrections 6/7/2022 MONICA RAMIREZ
Applicant returned to address corrections 2/24/2023 MONICA RAMIREZ
Applicant returned to address corrections 3/9/2023 MONICA RAMIREZ
Applicant returned to address corrections 3/18/2023 MONICA RAMIREZ
Applicant returned to address corrections 4/27/2023 MONICA RAMIREZ
Plan Check Approved 7/24/2023 MONICA RAMIREZ
Issued 1/4/2024 APPLICANT

Permit Application Clearance Information

HPOZ Cleared 7/11/2022 KATIE DEBIASE
Address approval Cleared 9/6/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/8/2022 CINDY QI
Grading Pre-Inspection Cleared 9/8/2022 KIRK LINKLATER
Sewer availability Cleared 9/8/2022 CINDY QI
Private street Cleared 9/14/2022 KENTON TRINH
Hydrant and Access approval Cleared 10/8/2022 GILBERT URREA
Low Impact Development Cleared 10/28/2022 ANTHONY VARGAS
GPI Written Notices Cleared 10/31/2022 MONICA RAMIREZ
Roof/Waste drainage to street Cleared 11/7/2022 CINDY QI
Permit Cleared 5/23/2023 CINDY QI
Public Works-Sewers Cleared 5/23/2023 CINDY QI
Public Works-Highway Ded. Cleared 5/23/2023 CINDY QI
Trees in Parkway Cleared 6/22/2023 ADALBERTO VERA

Contact Information

Contractor Bruce Lei Construction Inc; Lic. No.: 952042-B       ,
Engineer Yang,, Hongbo; Lic. No.: C88467 8457 TWEEDY LANE      DOWNEY, CA 90240

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/29/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/13/2024 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/11/2024 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 3/11/2024 Partial Approval HAMIK HARTOUNIAN
Insulation 3/14/2024 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 4/18/2024 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 4/18/2024 Corrections Issued BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/18/2024 Approved BRIAN SULLIVAN
Deputy Wood Construction 5/10/2024 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 5/14/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 5/14/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 6/18/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 6/18/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 6/18/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/17/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 10/17/2024 Approved THOMAS LOGRASSO
HVAC-Rough 10/17/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 11/15/2024 Approved THOMAS LOGRASSO
Insulation 11/15/2024 Partial Approval THOMAS LOGRASSO
Drywall Nailing 11/26/2024 Approved THOMAS LOGRASSO
Insulation 11/26/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 11/26/2024 Partial Approval THOMAS LOGRASSO
Service/Power Release 2/10/2025 Partial Inspection THOMAS LOGRASSO