2681 1/4 E POMEROY AVE 90033
Certificate Information: 2681 1/4 E POMEROY AVE 90033
- Application / Permit
- 22010-10000-01469
- Plan Check / Job No.
- B22LA05082
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | AUNG SOE |
| Corrections Issued | 5/5/2022 | AUNG SOE |
| Quality Review Completed | 5/5/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Applicant returned to address corrections | 7/7/2022 | AUNG SOE |
| Plan Check Approved | 7/15/2022 | AUNG SOE |
| Issued | 7/15/2022 | APPLICANT |
| CofO in Progress | 3/4/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
| CofO Issued | 3/9/2025 | DEROLD HAUFF |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/3/2022 | AUNG SOE |
| Address approval | Cleared | 6/6/2022 | TREVOR QUAN |
| Clean Up Green Up | Cleared | 6/7/2022 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 6/16/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 6/23/2022 | TREVOR QUAN |
| GPI Written Notices | Cleared | 7/7/2022 | AUNG SOE |
| Distance to fire station | Cleared | 7/9/2022 | RUEL COLE |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 625 N UNRUH AVE # 2 LA PUENTE, CA 91744 |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2022 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 9/16/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 2/10/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 2/10/2023 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/15/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/1/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/1/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/24/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/12/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/16/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/16/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/16/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/30/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/6/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 8/6/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Rough | 8/6/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/6/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Wood Construction | 8/8/2024 | Conditional Approval | OSVALDO PARAMO |
| Wood Frame | 8/9/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | LILIANA PORTILLO |
| Insulation | 8/26/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/30/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 8/30/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 8/30/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/30/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 9/11/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/13/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 9/13/2024 | Approved | OSVALDO PARAMO |
| Sewer | 12/17/2024 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 12/17/2024 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 2/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 2/24/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 2/24/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/24/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/27/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/4/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |