812 W AVENUE 37 90065

Certificate Information: 812 W AVENUE 37 90065

Application / Permit
22010-10000-01438
Plan Check / Job No.
B22LA04956
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY HOUSE WITH ATTACHED 2-CAR GARAGE AND ROOF DECK & PROVIDE FIRE SPRINKLERS NFPA 13-R IN LIEU OF MEETING THE REQUIRED DISTANCE TO A HYDRANT 1 OF 2
Permit Issued
Issued on 5/16/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 SERGIO GUTIERREZ
Corrections Issued 4/5/2022 SERGIO GUTIERREZ
Quality Review Completed 4/12/2022 FARUK SEZER
Building Plans Picked Up 4/26/2022 APPLICANT
Applicant returned to address corrections 7/13/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 11/4/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 5/1/2023 SERGIO GUTIERREZ
Plan Check Approved 5/16/2023 SERGIO GUTIERREZ
Issued 5/16/2023 APPLICANT
CofO in Progress 6/3/2025 ALIZAH MAYAGOITIA
Permit Finaled 6/8/2025 DEROLD HAUFF
CofO Issued 6/8/2025 DEROLD HAUFF
Permit Finaled 6/8/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/29/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 4/29/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/29/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/29/2022 CHRISTOPHER ROCHA
Trees in Parkway Cleared 6/17/2022 ADALBERTO VERA
Low Impact Development Cleared 8/18/2022 MITESH PATEL
Disturb/Remove Protected Trees Cleared 8/23/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 10/3/2022 KURT CORRAL
Stormwater Pollution Mitigatn Cleared 11/23/2022 SERGIO GUTIERREZ
Highway dedication Cleared 1/18/2023 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 2/6/2023 ARMEN MEHRABIAN
BHO/Hillside ordinance Cleared 2/6/2023 ARMEN MEHRABIAN
Permit Cleared 2/6/2023 ARMEN MEHRABIAN
Certificate of Compliance Cleared 2/15/2023 KENTON TRINH
Specific Plan Cleared 2/15/2023 KENTON TRINH
ZA Case Cleared 2/15/2023 KENTON TRINH
BHO/Hillside ordinance Cleared 3/3/2023 CHRISTOPHER ROCHA
GPI Written Notices Cleared 5/1/2023 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 5/1/2023 SERGIO GUTIERREZ
Roof/Waste drainage to street Cleared 5/11/2023 ARMEN MEHRABIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2023 Approved OSVALDO PARAMO
Deputy Grading 6/23/2023 Conditional Approval OSVALDO PARAMO
Deputy Grading 8/8/2023 Approved OSVALDO PARAMO
Deputy Reinf. Concrete 8/8/2023 Conditional Approval OSVALDO PARAMO
Piling/Pier/Caisson 8/8/2023 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 8/15/2023 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 9/28/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/6/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/10/2023 No Access for Inspection SCOTT FINNILA
Piling/Pier/Caisson 10/10/2023 No Access for Inspection SCOTT FINNILA
Footing/Foundation/Slab 10/11/2023 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 10/13/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/20/2023 Corrections Issued OSVALDO PARAMO
Reinforced Concrete Frame 10/20/2023 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 10/24/2023 Partial Approval OSVALDO PARAMO
Deputy Shotcrete 10/25/2023 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 11/9/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/16/2023 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 12/6/2023 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/7/2023 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 12/8/2023 Partial Approval OSVALDO PARAMO
Underground Mechanical 1/2/2024 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval CRAIG VAUGHAN
Insulation 2/21/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval OSVALDO PARAMO
Deputy Steel/Welding 3/4/2024 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/29/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/16/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 4/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/30/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 5/1/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 5/10/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/30/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 5/31/2024 Approved OSVALDO PARAMO
HVAC-Rough 5/31/2024 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 6/5/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 6/5/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 6/5/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/10/2024 Approved OSVALDO PARAMO
Green Building Rough 6/10/2024 Approved OSVALDO PARAMO
HVAC-Rough 6/10/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/11/2024 Partial Approval OSVALDO PARAMO
Underground Mechanical 6/11/2024 Not Ready for Inspection OSVALDO PARAMO
Insulation 6/14/2024 Approved OSVALDO PARAMO
Drywall Nailing 6/20/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/25/2024 Approved OSVALDO PARAMO
Shower Pan 6/25/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 10/1/2024 Not Ready for Inspection OSVALDO PARAMO
Service/Power Release 10/1/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 12/4/2024 Corrections Issued OSVALDO PARAMO
HVAC-Final 12/4/2024 Corrections Issued OSVALDO PARAMO
Underground Mechanical 12/4/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 12/12/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 12/19/2024 Approved BRENDAN MORELLI
PLUMBING-Final 1/29/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 1/29/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 2/11/2025 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 3/25/2025 Partial Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 3/28/2025 Approved ALIZAH MAYAGOITIA
Final 5/16/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/16/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 5/16/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Required ALIZAH MAYAGOITIA
Smoke Detectors 5/16/2025 Approved ALIZAH MAYAGOITIA
Final 6/2/2025 OK to Issue CofO ALIZAH MAYAGOITIA