14234 W TIARA ST 91401

Certificate Information: 14234 W TIARA ST 91401

Application / Permit
22010-10000-01408
Plan Check / Job No.
B22LA04862
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. CONVERT PORTION OF (E) GARAGE TO REC ROOM 286 SF AND 120 SF ADDITION AT 1ST FLOOR WITH 2ND STORY ADDITION OF 477 SF ADU
Permit Issued
Issued on 2/14/2023
Issuing Office
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 CRYSTEL MAALOUF
Corrections Issued 5/9/2022 CRYSTEL MAALOUF
Quality Review Completed 5/23/2022 FARUK SEZER
Applicant returned to address corrections 9/12/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 11/8/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 12/23/2022 CRYSTEL MAALOUF
Plan Check Approved 1/23/2023 CRYSTEL MAALOUF
Issued 2/14/2023 APPLICANT
CofO in Progress 7/24/2024 RYAN SALAZAR
No Progress 8/30/2024 ROBERT GOLD
CofO in Progress 8/30/2024 ROBERT GOLD
No Progress 8/14/2025 JOAQUIN GREENOUGH
CofO in Progress 8/14/2025 JOAQUIN GREENOUGH
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

"Q" conditions Cleared 7/25/2022 DANG NGUYEN
Address approval Cleared 7/25/2022 CARLOS AGUILERA
CPC Cleared 7/25/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 7/26/2022 CARLOS AGUILERA
Sewer availability Cleared 7/26/2022 CARLOS AGUILERA
Construction near power lines Cleared 10/14/2022 RIDWAN HARDY
Low Impact Development Cleared 11/8/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 11/14/2022 CARLOS AGUILERA

Contact Information

Contractor Hammerhead Construction; Lic. No.: 868943-B       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2023 Partial Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 7/5/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 7/5/2023 Approved RYAN SALAZAR
Underground Mechanical 7/5/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval RYAN SALAZAR
Green Building Rough 8/17/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval RYAN SALAZAR
Green Building Rough 9/6/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 11/7/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 11/7/2023 Corrections Issued RYAN SALAZAR
Green Building Rough 11/7/2023 Approved RYAN SALAZAR
HVAC-Rough 11/7/2023 Approved RYAN SALAZAR
PLUMBING-Rough 11/7/2023 Approved RYAN SALAZAR
Insulation 12/5/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/5/2023 Not Ready for Inspection RYAN SALAZAR
Shower Pan 12/5/2023 Approved RYAN SALAZAR
Drywall Nailing 12/12/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 12/12/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/31/2024 Approved RYAN SALAZAR
Final 5/31/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Final 5/31/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/31/2024 Approved RYAN SALAZAR
Final 7/23/2024 OK to Issue CofO RYAN SALAZAR
Special/Order Compliance 8/14/2025 Partial Approval JOAQUIN GREENOUGH