1316 W PAPEETE ST 90744
Certificate Information: 1316 W PAPEETE ST 90744
- Application / Permit
- 22010-10000-01407
- Plan Check / Job No.
- B22LA04860
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. NEW DETACHED 2- STORY ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Current Status
- CofO Issued on 7/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | MONICA RAMIREZ |
| Corrections Issued | 4/26/2022 | MONICA RAMIREZ |
| Quality Review Completed | 5/3/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 5/24/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 7/8/2022 | MONICA RAMIREZ |
| Plan Check Approved | 7/21/2022 | MONICA RAMIREZ |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 7/2/2024 | EUGENE CASSIDY |
| Permit Finaled | 7/8/2024 | ANSON MAGLASANG |
| CofO Issued | 7/8/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 5/3/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 5/25/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 6/22/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Lara Home Remodel Llc; Lic. No.: 1065220-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 2036 CREEK RD KITTY HAWK, NC 27949 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 11/29/2022 | Corrections Issued | JOHN KLARIN |
| METHANE-Barrier | 11/29/2022 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 11/29/2022 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/21/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Approved | JAMES CHAVEZ |
| Insulation | 12/22/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 12/27/2022 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 12/27/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| METHANE-Rough | 12/27/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 12/27/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Wood Frame | 12/29/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 1/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 1/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/10/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/17/2023 | Partial Approval | EUGENE CASSIDY |
| MERV13>=Rough | 1/17/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 1/17/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/17/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 1/19/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/14/2023 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Rough | 2/14/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 2/14/2023 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 2/21/2023 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/26/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/27/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/27/2023 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 4/27/2023 | Conditional Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/12/2023 | Approved | EUGENE CASSIDY |
| Gas Test | 5/12/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/12/2023 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 5/12/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/12/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/19/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 5/23/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/6/2023 | Corrections Issued | JOHN KLARIN |
| Interior/Exterior Lathing | 6/6/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 6/8/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/8/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/1/2023 | Partial Approval | EUGENE CASSIDY |
| Sewer | 9/1/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/16/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/16/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/24/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 10/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Gas Test | 11/20/2023 | Approved | EUGENE CASSIDY |
| Final | 4/26/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/26/2024 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 4/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 4/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 4/26/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/31/2024 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 5/31/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 5/31/2024 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 5/31/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/1/2024 | Approved | EUGENE CASSIDY |
| Final | 7/1/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 7/1/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 7/1/2024 | Approved | EUGENE CASSIDY |