3700 W BOYCE AVE 90039
Certificate Information: 3700 W BOYCE AVE 90039
- Application / Permit
- 22010-10000-01401
- Plan Check / Job No.
- B22LA04847
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Current Status
- CofO Issued on 8/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2022 | SELLA BENYAMIN |
| Corrections Issued | 3/21/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 8/2/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 8/6/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 8/9/2022 | KEVIN MORALES |
| Plan Check Approved | 8/17/2022 | SELLA BENYAMIN |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 5/24/2023 | JEFFREY MEAD |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
| CofO Issued | 8/6/2023 | DEROLD HAUFF |
| Permit Finaled | 8/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 4/4/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 6/1/2022 | RIDWAN HARDY |
Contact Information
| Architect | Lehrer,, Michael Berryl; Lic. No.: NA12115 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2022 | Partial Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 10/4/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/15/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/16/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/11/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/18/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/18/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/24/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/27/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/27/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 2/3/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 2/3/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/1/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 4/25/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/25/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/25/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/23/2023 | Approved | JEFFREY MEAD |
| Final | 5/23/2023 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 5/23/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/23/2023 | Approved | JEFFREY MEAD |