170 S MCCADDEN PL 90004

Certificate Information: 170 S MCCADDEN PL 90004

Application / Permit
22010-10000-01376
Plan Check / Job No.
B22LA04699
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERSION OF (E) 2-STORY ACCESSORY BUILDING, GARAGE AT GROUND FLOOR, TO ADU PER CA GC 65852.2(e)(1)(A). SECOND FLOOR STUDIO TO REMAIN. ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 4/15/2022
Issuing Office
Current Status
CofO Issued on 11/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 VIVIAN LAO
Corrections Issued 3/21/2022 VIVIAN LAO
Applicant returned to address corrections 3/30/2022 VIVIAN LAO
Plan Check Approved 4/15/2022 VIVIAN LAO
Issued 4/15/2022 APPLICANT
CofO in Progress 10/28/2022 JEFFREY MEAD
Permit Finaled 11/7/2022 DEROLD HAUFF
CofO Issued 11/7/2022 DEROLD HAUFF
Permit Finaled 11/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2022 TREVOR QUAN
Sewer availability Cleared 4/5/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/6/2022 TREVOR QUAN
HPOZ Cleared 4/12/2022 SUKI GERSHENHORN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/1/2022 Approved ADAM ESCOTO
HVAC-Rough 6/1/2022 Approved ADAM ESCOTO
PLUMBING-Rough 6/1/2022 Approved ADAM ESCOTO
Wood Frame 6/1/2022 Approved ADAM ESCOTO
BUILDING-Rough-Frame 6/6/2022 Corrections Issued ADAM ESCOTO
Insulation 6/6/2022 Conditional Approval ADAM ESCOTO
Sewer 6/6/2022 Approved ADAM ESCOTO
BUILDING-Rough-Frame 6/7/2022 Approved ADAM ESCOTO
Green Building Rough 6/7/2022 Approved ADAM ESCOTO
METHANE-Rough 6/7/2022 Approved ADAM ESCOTO
Drywall Nailing 6/14/2022 Approved ADAM ESCOTO
Footing/Foundation/Slab 6/21/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 6/21/2022 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Not Ready MICHAEL LEWIS
Final 10/19/2022 Corrections Issued MICHAEL LEWIS
Final 10/25/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Final 10/25/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 10/25/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 10/28/2022 Approved JEFFREY MEAD
Final 10/28/2022 OK to Issue CofO JEFFREY MEAD
HVAC-Final 10/28/2022 Approved JEFFREY MEAD
PLUMBING-Final 10/28/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved JEFFREY MEAD