9538 N BURNET AVE 91343
Certificate Information: 9538 N BURNET AVE 91343
- Application / Permit
- 22010-10000-01369
- Plan Check / Job No.
- B22LA04652
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d) ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2022 | FERNANDO FLORES |
| Corrections Issued | 3/29/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 3/31/2022 | APPLICANT |
| Applicant returned to address corrections | 8/18/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 8/23/2022 | ADAM HEGAZI |
| Plan Check Approved | 8/29/2022 | DANIEL SANJUAN |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 12/30/2022 | JENNIFER RABUCHIN |
| CofO Issued | 1/19/2023 | MICHAEL SMITH |
| Permit Finaled | 1/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/27/2022 | CARLOS AGUILERA |
| ZA Case | Cleared | 8/17/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 8/17/2022 | DALIA MOKAYED |
| Zoning Information File | Cleared | 8/18/2022 | KHUONG TRUONG |
| Low Impact Development | Cleared | 8/23/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/25/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 8/29/2022 | GILBERT URREA |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 9/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/30/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/3/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/3/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/3/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/3/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/11/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/11/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 11/4/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 11/4/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/1/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 12/1/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 12/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/27/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/27/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 12/27/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/27/2022 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/27/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 12/27/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/30/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 12/30/2022 | Approved | JENNIFER RABUCHIN |