15108 W MARTHA ST 91411

Certificate Information: 15108 W MARTHA ST 91411

Application / Permit
22010-10000-01355
Plan Check / Job No.
B22LA04616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 8/4/2022
Issuing Office
Current Status
Issued on 8/4/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/24/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 DANIEL YIP
Corrections Issued 3/27/2022 DANIEL YIP
Plan Check Approved 7/29/2022 DANIEL YIP
Issued 8/4/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/12/2022 CHRIS CHAHBAZ
ZI Cleared 4/21/2022 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 6/6/2022 CHRIS CHAHBAZ
Sewer availability Cleared 6/6/2022 CHRIS CHAHBAZ
Low Impact Development Cleared 6/29/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/5/2022 CARLOS AGUILERA

Contact Information

Contractor Best Builders & Development Inc; Lic. No.: 850444-B       ,
Engineer Hsiao,, Stephanie; Lic. No.: C75937 255 N MICHIGAN AVE #5      PASADENA, CA 91106

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/12/2022 Partial Approval JACK KARGODORIAN
Pre-Inspection 9/12/2022 Partial Inspection JACK KARGODORIAN
Footing/Foundation/Slab 9/15/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 9/21/2022 No Access for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 9/30/2022 Not Ready for Inspection RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 10/6/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 11/10/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/15/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/12/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/12/2023 Partial Approval RYAN SALAZAR
HVAC-Rough 1/12/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/30/2023 Partial Approval RYAN SALAZAR
Insulation 2/2/2023 Approved RYAN SALAZAR
Shower Pan 2/2/2023 Approved RYAN SALAZAR
Drywall Nailing 2/9/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 2/9/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/24/2023 Approved RYAN SALAZAR
Final 8/24/2023 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 8/24/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 8/24/2023 Approved RYAN SALAZAR
Final 12/4/2024 Not Ready for Inspection RYAN SALAZAR