1039 N ILIFF ST 90272
Certificate Information: 1039 N ILIFF ST 90272
- Application / Permit
- 22010-10000-01351
- Plan Check / Job No.
- B22LA04612
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- CofO Issued on 1/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2022 | CARLOS MONTES |
| Corrections Issued | 3/23/2022 | CARLOS MONTES |
| Plan Check Approved | 5/26/2022 | CARLOS MONTES |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 10/11/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/2/2024 | DANIEL ORRANTE |
| CofO Issued | 1/2/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/2/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 4/8/2022 | JOSE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 4/15/2022 | SERGIO VALENZUELA |
| Construction near power lines | Cleared | 4/20/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 4/27/2022 | DWIGHT SANKEY |
Contact Information
| Contractor | Lyons Development; Lic. No.: 969576-B | 10100 SANTA MONICA BLVD STE 314 LOS ANGELES, CA 90067 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/1/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 8/8/2022 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 8/31/2022 | Conditional Approval | KEVIN SARGSYAN |
| Sewer | 9/12/2022 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 11/22/2022 | Conditional Approval | KENNETH NAGLE |
| PLUMBING-Rough | 11/22/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 12/2/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/10/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 2/1/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 2/22/2023 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 3/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 3/2/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/2/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 3/9/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/16/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/16/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/16/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/29/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/31/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/5/2023 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 4/11/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/11/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/11/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/12/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/12/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 4/14/2023 | Approved | JESUS PINEDA |
| Underground Mechanical | 4/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/21/2023 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 4/21/2023 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/28/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/1/2023 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Final | 9/1/2023 | Corrections Issued | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 9/15/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/21/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/3/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 10/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 10/10/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |