1351 S REDONDO BLVD 90019

Certificate Information: 1351 S REDONDO BLVD 90019

Application / Permit
22010-10000-01287
Plan Check / Job No.
B22LA04524
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan PROPOSED 2 STORY ADU PER Standard ADU Plan #32
Permit Issued
Issued on 11/14/2022
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 CRYSTEL MAALOUF
Corrections Issued 4/26/2022 CRYSTEL MAALOUF
Quality Review Completed 5/23/2022 FARUK SEZER
Applicant returned to address corrections 6/29/2022 CRYSTEL MAALOUF
Plan Check Approved 9/2/2022 CRYSTEL MAALOUF
Issued 11/14/2022 APPLICANT
CofO in Progress 12/22/2023 ALIZAH MAYAGOITIA
CofO in Progress 1/3/2024 ALIZAH MAYAGOITIA
CofO Issued 1/10/2024 DEROLD HAUFF
Permit Finaled 1/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/31/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/1/2022 TREVOR QUAN
Low Impact Development Cleared 6/27/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/28/2022 TREVOR QUAN

Contact Information

Architect Yun,, Geunwoo; Lic. No.: C28833 10940 ODELL AVENUE      SUNLAND, CA 91040
Contractor Nelson General Building Contractor; Lic. No.: 649194-B 4227 S WESTERN AVE      LOS ANGELES, CA 90062
Engineer Kim,, Taewon; Lic. No.: C80632 2320 SANTA CRUZ CT      TORRANCE, CA 90501

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/6/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/6/2022 Corrections Issued JOSE AVILA
METHANE-Barrier 12/6/2022 Approved JOSE AVILA
METHANE-Subgrade 12/6/2022 Approved JOSE AVILA
Footing/Foundation/Slab 1/20/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval JOSE AVILA
Insulation 1/23/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Corrections Issued MICHAEL LEWIS
Wood Frame 2/8/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 4/20/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 4/20/2023 Approved STUART CHAPMAN
HVAC-Rough 4/20/2023 Approved STUART CHAPMAN
PLUMBING-Rough 4/20/2023 Corrections Issued STUART CHAPMAN
Insulation 4/26/2023 Partial Inspection STUART CHAPMAN
BUILDING-Rough-Frame 5/2/2023 Partial Approval JOSE AVILA
Green Building Rough 5/2/2023 Approved JOSE AVILA
Insulation 5/2/2023 Approved JOSE AVILA
METHANE-Rough 5/2/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 5/2/2023 Approved JOSE AVILA
Drywall Nailing 5/16/2023 Approved JOSE AVILA
Interior/Exterior Lathing 5/16/2023 Approved JOSE AVILA
Shower Pan 5/16/2023 Partial Approval JOSE AVILA
Interior/Exterior Lathing 6/6/2023 Approved JOSE AVILA
Sewer 6/21/2023 Approved JOSE AVILA
Underground Mechanical 8/2/2023 Corrections Issued JOSE AVILA
Underground Mechanical 8/24/2023 Approved JOSE AVILA
ELECTRICAL-Final 10/26/2023 Corrections Issued RONNIE MINDANAO
HVAC-Final 10/26/2023 Approved RONNIE MINDANAO
PLUMBING-Final 10/26/2023 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV No Gas RONNIE MINDANAO
Service/Power Release 10/26/2023 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 10/26/2023 Approved RONNIE MINDANAO
ELECTRICAL-Final 10/31/2023 Approved JOSE AVILA
Final 10/31/2023 Corrections Issued JOSE AVILA
Green Building Final 10/31/2023 Approved JOSE AVILA
PLUMBING-Final 10/31/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 12/21/2023 Approved ALIZAH MAYAGOITIA
Final 12/21/2023 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 12/21/2023 Approved ALIZAH MAYAGOITIA
Final 1/2/2024 OK to Issue CofO ALIZAH MAYAGOITIA