1351 S REDONDO BLVD 90019
Certificate Information: 1351 S REDONDO BLVD 90019
- Application / Permit
- 22010-10000-01287
- Plan Check / Job No.
- B22LA04524
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan PROPOSED 2 STORY ADU PER Standard ADU Plan #32
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 4/26/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/23/2022 | FARUK SEZER |
| Applicant returned to address corrections | 6/29/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/2/2022 | CRYSTEL MAALOUF |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 12/22/2023 | ALIZAH MAYAGOITIA |
| CofO in Progress | 1/3/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 1/10/2024 | DEROLD HAUFF |
| Permit Finaled | 1/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 6/27/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/28/2022 | TREVOR QUAN |
Contact Information
| Architect | Yun,, Geunwoo; Lic. No.: C28833 | 10940 ODELL AVENUE SUNLAND, CA 91040 |
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2320 SANTA CRUZ CT TORRANCE, CA 90501 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/6/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Barrier | 12/6/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 12/6/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 1/20/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | JOSE AVILA |
| Insulation | 1/23/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Corrections Issued | MICHAEL LEWIS |
| Wood Frame | 2/8/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 4/20/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/20/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 4/20/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/20/2023 | Corrections Issued | STUART CHAPMAN |
| Insulation | 4/26/2023 | Partial Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/2/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 5/2/2023 | Approved | JOSE AVILA |
| Insulation | 5/2/2023 | Approved | JOSE AVILA |
| METHANE-Rough | 5/2/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 5/2/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 5/16/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/16/2023 | Approved | JOSE AVILA |
| Shower Pan | 5/16/2023 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 6/6/2023 | Approved | JOSE AVILA |
| Sewer | 6/21/2023 | Approved | JOSE AVILA |
| Underground Mechanical | 8/2/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 8/24/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 10/26/2023 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 10/26/2023 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/26/2023 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV No Gas | RONNIE MINDANAO |
| Service/Power Release | 10/26/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 10/26/2023 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/31/2023 | Approved | JOSE AVILA |
| Final | 10/31/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 10/31/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 10/31/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/21/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/21/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/2/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |