9135 N NOBLE AVE 91343
Certificate Information: 9135 N NOBLE AVE 91343
- Application / Permit
- 22010-10000-01264
- Plan Check / Job No.
- B22LA04421
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Servant's Quarters
- Work Description
- (N) 2-STORY SERVANT QUARTER (NFPA 13D THRU OUT)
- Permit Issued
- Issued on 4/24/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | AUNG SOE |
| Corrections Issued | 4/26/2022 | AUNG SOE |
| Quality Review Completed | 4/28/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Applicant returned to address corrections | 10/3/2022 | AUNG SOE |
| Plan Check Approved | 10/25/2022 | AUNG SOE |
| Issued | 4/24/2023 | APPLICANT |
| CofO in Progress | 8/23/2024 | VINCENT HANLEY |
| Permit Finaled | 9/4/2024 | DANIEL ORRANTE |
| CofO Issued | 9/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/24/2022 | DANIEL CORONADO |
| Tract Map conditions | Cleared | 5/24/2022 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/1/2022 | DAGOVERTO GUERRERO |
| Certificate of Compliance | Cleared | 7/25/2022 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 8/3/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 9/1/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/14/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Park Jongwon Smart A C; Lic. No.: 1004833-B | 17704 SUPERIOR ST NORTHRIDGE, CA 91325 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 5/4/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/27/2023 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/27/2023 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/11/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/11/2023 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 7/11/2023 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 7/11/2023 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Approved | DAVID MATSON |
| PLUMBING-Rough | 7/19/2023 | Partial Approval | DAVID MATSON |
| Underground Mechanical | 8/23/2023 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 8/31/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 8/31/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 9/21/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 9/25/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 9/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/16/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/23/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/29/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/5/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/5/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 1/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 1/11/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/17/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 1/17/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/17/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/26/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/31/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/12/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/12/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 3/5/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/29/2024 | Approved | KIRK SANDERS |
| Final | 7/24/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/24/2024 | Approved | VINCENT HANLEY |
| Green Building Final | 7/24/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 7/24/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 7/24/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/15/2024 | Approved | VINCENT HANLEY |
| Final | 8/15/2024 | Partial Inspection | VINCENT HANLEY |
| HVAC-Final | 8/15/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/15/2024 | Approved | VINCENT HANLEY |
| Final | 8/23/2024 | OK to Issue CofO | VINCENT HANLEY |