716 1/2 N HARPER AVE 90046
Certificate Information: 716 1/2 N HARPER AVE 90046
- Application / Permit
- 22010-10000-01251
- Plan Check / Job No.
- B22LA04350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert a portion of existing Carport to 1st floor Accessory Dwelling Unit with 2nd Floor Addition for ADU.
- Permit Issued
- Issued on 8/20/2022
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | PRANITA SHAH |
| Corrections Issued | 4/19/2022 | PRANITA SHAH |
| Quality Review Completed | 4/29/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/16/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 8/5/2022 | PRANITA SHAH |
| Plan Check Approved | 8/18/2022 | PRANITA SHAH |
| Issued | 8/20/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | LILIANA PORTILLO |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 5/31/2022 | RIDWAN HARDY |
| Sewer availability | Cleared | 6/23/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 7/6/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | STEVE MELGAR |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | National Construction; Lic. No.: 894730-B | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 9/27/2022 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/26/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/26/2022 | Approved | MICHAEL LEWIS |
| Structural Steel Frame | 10/26/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 3/9/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 4/5/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 4/13/2023 | Approved | MICHAEL LEWIS |
| Insulation | 4/17/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/1/2023 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 5/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 5/8/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 5/8/2023 | Approved | LILIANA PORTILLO |
| Sewer | 5/8/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/8/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 5/12/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/12/2023 | Approved | LILIANA PORTILLO |
| Final | 8/7/2023 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 8/7/2023 | Approved | LILIANA PORTILLO |
| Green Building Final | 8/7/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 8/7/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 8/7/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 8/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 8/11/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 8/24/2023 | Approved | LILIANA PORTILLO |
| Final | 8/24/2023 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 8/24/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/24/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 8/24/2023 | Approved | LILIANA PORTILLO |