716 1/2 N HARPER AVE 90046

Certificate Information: 716 1/2 N HARPER AVE 90046

Application / Permit
22010-10000-01251
Plan Check / Job No.
B22LA04350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert a portion of existing Carport to 1st floor Accessory Dwelling Unit with 2nd Floor Addition for ADU.
Permit Issued
Issued on 8/20/2022
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 PRANITA SHAH
Corrections Issued 4/19/2022 PRANITA SHAH
Quality Review Completed 4/29/2022 HERNAN ARREOLA
Applicant returned to address corrections 5/16/2022 PRANITA SHAH
Applicant returned to address corrections 8/5/2022 PRANITA SHAH
Plan Check Approved 8/18/2022 PRANITA SHAH
Issued 8/20/2022 APPLICANT
CofO in Progress 8/25/2023 LILIANA PORTILLO
Permit Finaled 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/6/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/26/2022 JEANETTE VONG
Construction near power lines Cleared 5/31/2022 RIDWAN HARDY
Sewer availability Cleared 6/23/2022 JEANETTE VONG
Low Impact Development Cleared 7/6/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/13/2022 STEVE MELGAR

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor National Construction; Lic. No.: 894730-B       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Approval MICHAEL LEWIS
Underground Mechanical 9/27/2022 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/26/2022 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/26/2022 Approved MICHAEL LEWIS
Structural Steel Frame 10/26/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved MICHAEL LEWIS
Deputy Wood Construction 3/9/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 4/5/2023 Approved MICHAEL LEWIS
HVAC-Rough 4/5/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 4/5/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 4/13/2023 Approved MICHAEL LEWIS
Insulation 4/17/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/1/2023 Partial Approval LILIANA PORTILLO
Underground Mechanical 5/1/2023 Corrections Issued LILIANA PORTILLO
Drywall Nailing 5/8/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 5/8/2023 Approved LILIANA PORTILLO
Sewer 5/8/2023 Approved LILIANA PORTILLO
Shower Pan 5/8/2023 Approved LILIANA PORTILLO
Drywall Nailing 5/12/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/12/2023 Approved LILIANA PORTILLO
Final 8/7/2023 Corrections Issued LILIANA PORTILLO
Gas Test 8/7/2023 Approved LILIANA PORTILLO
Green Building Final 8/7/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 8/7/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 8/7/2023 Corrections Issued LILIANA PORTILLO
Final 8/11/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 8/11/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/24/2023 Approved LILIANA PORTILLO
Final 8/24/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 8/24/2023 Approved LILIANA PORTILLO
PLUMBING-Final 8/24/2023 Approved LILIANA PORTILLO
Service/Power Release 8/24/2023 Approved LILIANA PORTILLO