3985 S MCLAUGHLIN AVE 90066

Certificate Information: 3985 S MCLAUGHLIN AVE 90066

Application / Permit
22010-10000-01245
Plan Check / Job No.
B22LA04338
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
DETACHED GARAGE (REAR) 2 OF 3
Permit Issued
Issued on 11/4/2022
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 ADRIANA LOPEZ
Corrections Issued 3/31/2022 ADRIANA LOPEZ
Quality Review Completed 4/5/2022 SEAN DANG
Plan Check Approved 7/14/2022 ADRIANA LOPEZ
Issued 11/4/2022 APPLICANT
Building Plans Picked Up 11/7/2022 APPLICANT
CofO in Progress 5/22/2024 JESUS RODRIGUEZ
Permit Finaled 5/29/2024 DANIEL ORRANTE
CofO Issued 5/29/2024 DANIEL ORRANTE
Permit Finaled 5/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2022 DINAH GARIN
Sewer availability Cleared 6/3/2022 DINAH GARIN
Low Impact Development Cleared 6/28/2022 TA ANH
Roof/Waste drainage to street Cleared 6/28/2022 DINAH GARIN

Contact Information

Contractor Zepeda Juan; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 2/22/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/3/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/3/2023 Approved JESUS RODRIGUEZ
Green Building Rough 7/3/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/3/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/3/2023 Approved JESUS RODRIGUEZ
Wood Frame 7/3/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/10/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/10/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/10/2023 Approved JESUS RODRIGUEZ
Wood Frame 7/10/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 7/31/2023 Approved JESUS RODRIGUEZ
Final 4/22/2024 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Final 4/22/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Not Required JESUS RODRIGUEZ
Service/Power Release 4/22/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 5/10/2024 Approved JESUS RODRIGUEZ
Final 5/10/2024 Partial Approval JESUS RODRIGUEZ
Final 5/22/2024 OK to Issue CofO JESUS RODRIGUEZ