10351 W KESWICK AVE 90064
Certificate Information: 10351 W KESWICK AVE 90064
- Application / Permit
- 22010-10000-01216
- Plan Check / Job No.
- B22LA04217
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW 2-STORY ADU per Ordinance LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | MONICA RAMIREZ |
| Corrections Issued | 4/13/2022 | MONICA RAMIREZ |
| Quality Review Completed | 4/16/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/21/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/13/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/23/2023 | MONICA RAMIREZ |
| Plan Check Approved | 2/2/2023 | MONICA RAMIREZ |
| Issued | 2/9/2023 | APPLICANT |
| CofO in Progress | 10/1/2025 | DANIEL VERA |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/25/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2022 | STEVEN JIN |
| Sewer availability | Cleared | 4/30/2022 | STEVEN JIN |
| Address approval | Cleared | 5/5/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 9/29/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 10/10/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 12/13/2022 | MONICA RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yang,, Hongbo; Lic. No.: C88467 | 8457 TWEEDY LANE DOWNEY, CA 90240 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/11/2023 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/11/2023 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/12/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/31/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/11/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/5/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 12/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 12/27/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/18/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/18/2024 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Rough | 1/18/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/18/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/18/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 3/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 3/22/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 3/27/2024 | Approved | STEPHANIE SWANSON |
| Final | 3/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 5/9/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/14/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/14/2025 | Approved | DANIEL VERA |
| Final | 3/14/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 3/14/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 3/14/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Approved | DANIEL VERA |
| Service/Power Release | 3/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 3/14/2025 | Approved | DANIEL VERA |
| Final | 7/31/2025 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 7/31/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 8/21/2025 | Approved | DANIEL VERA |
| Final | 9/30/2025 | OK to Issue CofO | DANIEL VERA |
| Service/Power Release | 9/30/2025 | Approved | DANIEL VERA |