3530 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3530 S MOUNTAIN VIEW AVE 90066

Application / Permit
22010-10000-01138
Plan Check / Job No.
B22LA04166
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
DETACHED PATIO COVER
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 5/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 MAHNAZ NOURHASHEMI
Corrections Issued 3/25/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 3/30/2022 KEN GILL
Building Plans Picked Up 4/27/2022 APPLICANT
Applicant returned to address corrections 5/25/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 7/12/2022 MAHNAZ NOURHASHEMI
Issued 7/14/2022 APPLICANT
CofO in Progress 5/7/2025 WILBER ROSALES
Permit Finaled 5/9/2025 RICHARD STEINBACH
CofO Issued 5/9/2025 RICHARD STEINBACH
Permit Finaled 5/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 5/14/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 5/16/2022 SAUL GARCIA
Low Impact Development Cleared 5/18/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 5/20/2022 SAUL GARCIA
GPI Written Notices Cleared 6/28/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 6/28/2022 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 9/14/2022 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 9/15/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 6/13/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 7/2/2024 Not Ready for Inspection JESUS PINEDA
Special/Order Compliance 7/3/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 7/17/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 7/26/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 7/26/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 10/1/2024 Approved DANIEL VERA
PLUMBING-Rough 10/1/2024 Approved DANIEL VERA
Underground Mechanical 10/1/2024 Approved DANIEL VERA
Deputy Wood Construction 10/29/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved DANIEL VERA
Rough-Elec/Plmb/HVAC 11/5/2024 Approved DANIEL VERA
Interior/Exterior Lathing 12/6/2024 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 12/12/2024 Approved TEMISTOCLES CAAL
Green Building Rough 12/12/2024 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 12/12/2024 Approved TEMISTOCLES CAAL
Insulation 12/17/2024 Approved DANIEL VERA
Drywall Nailing 12/19/2024 Approved DANIEL VERA
Final 5/1/2025 Corrections Issued WILBER ROSALES
Green Building Final 5/1/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/1/2025 SGSOV Approved WILBER ROSALES
Service/Power Release 5/1/2025 Not Required WILBER ROSALES
Smoke Detectors 5/1/2025 Approved WILBER ROSALES
ELECTRICAL-Final 5/2/2025 Approved WILBER ROSALES
HVAC-Final 5/2/2025 Approved WILBER ROSALES
PLUMBING-Final 5/2/2025 Approved WILBER ROSALES
Final 5/7/2025 OK to Issue CofO WILBER ROSALES