3530 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3530 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22010-10000-01138
- Plan Check / Job No.
- B22LA04166
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- DETACHED PATIO COVER
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofO Issued on 5/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/25/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/30/2022 | KEN GILL |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| Applicant returned to address corrections | 5/25/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/12/2022 | MAHNAZ NOURHASHEMI |
| Issued | 7/14/2022 | APPLICANT |
| CofO in Progress | 5/7/2025 | WILBER ROSALES |
| Permit Finaled | 5/9/2025 | RICHARD STEINBACH |
| CofO Issued | 5/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/14/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | SAUL GARCIA |
| Low Impact Development | Cleared | 5/18/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/20/2022 | SAUL GARCIA |
| GPI Written Notices | Cleared | 6/28/2022 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 6/28/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/14/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/15/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/2/2024 | Not Ready for Inspection | JESUS PINEDA |
| Special/Order Compliance | 7/3/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/17/2024 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 7/26/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 7/26/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 10/1/2024 | Approved | DANIEL VERA |
| PLUMBING-Rough | 10/1/2024 | Approved | DANIEL VERA |
| Underground Mechanical | 10/1/2024 | Approved | DANIEL VERA |
| Deputy Wood Construction | 10/29/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | DANIEL VERA |
| Rough-Elec/Plmb/HVAC | 11/5/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 12/12/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 12/12/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 12/17/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 12/19/2024 | Approved | DANIEL VERA |
| Final | 5/1/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/1/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 5/1/2025 | Not Required | WILBER ROSALES |
| Smoke Detectors | 5/1/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 5/2/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 5/2/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 5/2/2025 | Approved | WILBER ROSALES |
| Final | 5/7/2025 | OK to Issue CofO | WILBER ROSALES |