1331 1/2 W 85TH ST 90044
Certificate Information: 1331 1/2 W 85TH ST 90044
- Application / Permit
- 22010-10000-01112
- Plan Check / Job No.
- B22LA04102
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (eplan) 2-STORY ADDITION OF ACCESSORY DWELLING UNIT (A.D.U) TO EXISTING DETACHED GARAGE PER LAMC 12.22.A.33(c)-(d) "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- Current Status
- Issued on 11/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | YOUNG KIM |
| Corrections Issued | 5/17/2022 | YOUNG KIM |
| Quality Review Completed | 6/2/2022 | FARUK SEZER |
| Applicant returned to address corrections | 3/8/2024 | YOUNG KIM |
| Applicant returned to address corrections | 3/27/2024 | YOUNG KIM |
| Plan Check Approved | 5/27/2024 | YOUNG KIM |
| Issued | 11/26/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2022 | PAMELA TENEZA |
| Sewer availability | Cleared | 9/7/2022 | PAMELA TENEZA |
| Low Impact Development (LID) | Cleared | 5/27/2024 | LUIS LUVANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2025 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 12/12/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 12/12/2025 | Approved | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 1/15/2026 | No Access for Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 1/21/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 6/3/2026 | Partial Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/3/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/17/2026 | Approved | RAUL BARAJAS |
| Green Building Rough | 6/17/2026 | Approved | RAUL BARAJAS |