217 E VERNON AVE 90011
Certificate Information: 217 E VERNON AVE 90011
- Application / Permit
- 22010-10000-01111
- Plan Check / Job No.
- B22LA04099
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 13 UNITS (100% AFFORDABLE HOUSING) APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT, TIER 4 TOC WITH BASE INCENTIVE
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Current Status
- Issued on 11/2/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | MANUEL MONTUFAR |
| Corrections Issued | 3/30/2022 | MANUEL MONTUFAR |
| Quality Review Completed | 4/1/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/31/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 9/16/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 9/28/2022 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 8/24/2023 | MANUEL MONTUFAR |
| Plan Check Approved | 8/28/2023 | MANUEL MONTUFAR |
| Issued | 11/2/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | JEANETTE VONG |
| Bicycle Parking | Cleared | 4/18/2022 | JEREMY CHOK |
| Building over 36-ft | Cleared | 6/16/2022 | CALOSHA APPROVED |
| Trees in Parkway | Cleared | 7/13/2022 | ADALBERTO VERA |
| Highway dedication | Cleared | 9/27/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 10/1/2022 | RUEL COLE |
| Low Impact Development | Cleared | 1/20/2023 | TA ANH |
| Fire Marshal Fire Life Safety | Cleared | 1/25/2023 | DOMINIQUE MEDINA |
| Permit | Cleared | 1/27/2023 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/27/2023 | JEANETTE VONG |
| Frnt yard landscape/Water mgmt | Cleared | 1/30/2023 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 1/30/2023 | MAXFIELD VERMY |
| Opn space landscape/Water mgmt | Cleared | 1/30/2023 | MAXFIELD VERMY |
| Sewer availability | Cleared | 1/31/2023 | JEANETTE VONG |
| Historic Resource Verification | Cleared | 4/11/2023 | MAX LODER |
| Redevelopment Project Area | Cleared | 4/13/2023 | DAVID URITA |
| Green Code | Cleared | 5/9/2023 | AARON COSTA |
| Density Bonus 12.22.A.31 | Cleared | 6/6/2023 | JAMES MCCARTHY |
| DAS Clearance | Cleared | 8/28/2023 | MANUEL MONTUFAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Parvini,, Mehdi; Lic. No.: C63186 | 1226 SOUZA DRIVE EL DORADO HILLS, CA 95762 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2024 | No Access for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 5/1/2024 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/9/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 5/31/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/31/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 6/3/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 6/20/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 6/24/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/24/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 7/24/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/24/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/24/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 8/16/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/16/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 8/29/2024 | Partial Approval | JAMES POWERS |
| Pre-Inspection | 1/29/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 4/2/2025 | Approved | RAFAEL ESPINOZA |