19148 W ARCHWOOD ST 91335

Certificate Information: 19148 W ARCHWOOD ST 91335

Application / Permit
22010-10000-01108
Plan Check / Job No.
B22LA04086
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE
Permit Issued
Issued on 9/5/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 JOSEPH RAFOLS
Corrections Issued 3/12/2022 JOSEPH RAFOLS
Building Plans Picked Up 3/14/2022 APPLICANT
Plan Check Approved 5/19/2022 DANIEL SANJUAN
Plan Check Approved 9/5/2024 FERNANDO FLORES
Issued 9/5/2024 APPLICANT
CofO in Progress 3/25/2025 ARUTYUN MADATYAN
Permit Finaled 4/16/2025 JOHN JANSON
CofO Issued 4/16/2025 JOHN JANSON
Permit Finaled 4/16/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/16/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/16/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/16/2022 JOSE DUARTE-DIAZ
ZI Cleared 3/21/2022 DANIEL CORONADO
Construction near power lines Cleared 4/23/2022 RIDWAN HARDY
Low Impact Development Cleared 5/6/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/9/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Prestige Remodeling; Lic. No.: 1104743-B 19152 ARCHWOOD ST      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2024 Approved JEFFREY BULL
Underground Mechanical 9/30/2024 Partial Approval JEFFREY BULL
Footing/Foundation/Slab 10/8/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Approved JEFFREY BULL
Green Building Rough 10/28/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 11/8/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 11/8/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 11/8/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/13/2024 Approved ARUTYUN MADATYAN
Green Building Rough 11/13/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 11/13/2024 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 11/19/2024 Approved KRISTEN CAUSEY
Shower Pan 11/26/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 12/2/2024 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 1/27/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 1/27/2025 Approved ARUTYUN MADATYAN
HVAC-Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 1/27/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/24/2025 Approved ARUTYUN MADATYAN
Final 3/24/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 3/24/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 3/24/2025 Approved ARUTYUN MADATYAN
Service/Power Release 3/24/2025 Approved ARUTYUN MADATYAN