10050-10052 PINEWOOD AVE 91042

Certificate Information: 10050-10052 PINEWOOD AVE 91042

Application / Permit
22010-10000-01105
Plan Check / Job No.
B22LA04075
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 NEW 1200 SQFT ADU EACH FOR LOT
Permit Issued
Issued on 8/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 JAD BASMA
Corrections Issued 3/30/2022 JAD BASMA
Quality Review Completed 4/6/2022 KEN GILL
Building Plans Picked Up 4/12/2022 APPLICANT
Plan Check Approved 1/12/2023 JAD BASMA
Issued 8/3/2023 APPLICANT
CofO in Progress 5/28/2025 WILLIAM WREN
Permit Finaled 6/12/2025 RUBEN SALAS
CofO Issued 6/12/2025 RUBEN SALAS
Permit Finaled 6/12/2025 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/13/2022 CINDY JOSSELYN
Address approval Cleared 7/1/2022 DAGOVERTO GUERRERO
Address approval Cleared 7/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 11/2/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 11/16/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/22/2022 DAGOVERTO GUERRERO
ZI Cleared 12/12/2022 SARAH HOUNSELL
GPI Written Notices Cleared 1/12/2023 JAD BASMA
Grading Pre-Inspection Cleared 1/12/2023 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2023 Corrections Issued WILLIAM WREN
Pre-Inspection 9/6/2023 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 9/8/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 10/11/2023 Not Ready for Inspection WILLIAM WREN
Underground Mechanical 10/11/2023 Corrections Issued WILLIAM WREN
Underground Mechanical 11/14/2023 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 11/17/2023 Partial Approval WILLIAM WREN
PLUMBING-Rough 11/17/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 11/22/2023 Partial Approval WILLIAM WREN
Insulation 11/27/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Approved WILLIAM WREN
Green Building Rough 12/18/2023 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 12/18/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 2/7/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Corrections Issued WILLIAM WREN
Green Building Rough 2/7/2024 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 2/7/2024 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 2/7/2024 Approved WILLIAM WREN
Verify Sprinkler Sign Off 2/7/2024 Approved WILLIAM WREN
Deputy Wood Construction 2/8/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 2/21/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 2/21/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Approved WILLIAM WREN
Green Building Rough 2/21/2024 Approved WILLIAM WREN
PLUMBING-Rough 2/21/2024 Approved WILLIAM WREN
Verify Sprinkler Sign Off 2/21/2024 Approved WILLIAM WREN
Insulation 4/11/2024 Corrections Issued WILLIAM WREN
Drywall Nailing 5/2/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 5/2/2024 Approved WILLIAM WREN
Shower Pan 5/2/2024 Approved WILLIAM WREN
Final 11/18/2024 Not Ready for Inspection WILLIAM WREN
Green Building Final 11/18/2024 Not Ready for Inspection WILLIAM WREN
Pre-Inspection 11/18/2024 Partial Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 11/18/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Ready WILLIAM WREN
Service/Power Release 4/29/2025 Not Ready for Inspection WILLIAM WREN
Final 5/7/2025 Not Ready for Inspection WILLIAM WREN
Green Building Final 5/7/2025 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Not Ready WILLIAM WREN
Service/Power Release 5/7/2025 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 5/7/2025 Not Ready for Inspection WILLIAM WREN
Final 5/9/2025 Corrections Issued WILLIAM WREN
Green Building Final 5/9/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Required WILLIAM WREN
Service/Power Release 5/9/2025 Approved WILLIAM WREN
Smoke Detectors 5/9/2025 Approved WILLIAM WREN
Final 5/21/2025 OK to Issue CofO WILLIAM WREN
ELECTRICAL-Final 5/27/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Final 5/27/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 5/27/2025 Approved NICHOLAS TROWBRIDGE
Final 5/28/2025 Not Ready for Inspection WILLIAM WREN