5262 E ALDAMA ST 90042

Certificate Information: 5262 E ALDAMA ST 90042

Application / Permit
22010-10000-01089
Plan Check / Job No.
B22LA03967
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER DETACHED ADU STATE LAW (1-STORY) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 8/11/2022
Issuing Office
Current Status
CofO Issued on 5/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 CARLOS MONTES
Corrections Issued 3/26/2022 CARLOS MONTES
Quality Review Completed 3/30/2022 LIPING TENG
Applicant returned to address corrections 7/12/2022 CARLOS MONTES
Applicant returned to address corrections 7/20/2022 CARLOS MONTES
Plan Check Approved 8/9/2022 CARLOS MONTES
Issued 8/11/2022 APPLICANT
CofO in Progress 5/25/2023 SCOTT FINNILA
Permit Finaled 5/28/2023 DEROLD HAUFF
CofO Issued 5/28/2023 DEROLD HAUFF
Permit Finaled 5/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/13/2022 JEANETTE VONG
CPC Cleared 4/13/2022 KATIE DEBIASE
HPOZ Cleared 4/13/2022 KATIE DEBIASE
Street Frontage Cleared 4/13/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/11/2022 JEANETTE VONG
Sewer availability Cleared 5/11/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 7/1/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 7/20/2022 CARLOS MONTES
GPI Written Notices Cleared 8/9/2022 CARLOS MONTES

Contact Information

Contractor Lund Construction; Lic. No.: 982798-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/23/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/23/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 9/23/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/5/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 12/5/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 12/5/2022 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 12/5/2022 Conditional Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 12/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/20/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 1/20/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/20/2023 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/20/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/25/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/25/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/31/2023 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 1/31/2023 Approved HAMIK HARTOUNIAN
Insulation 1/31/2023 Corrections Issued HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 1/31/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/10/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/10/2023 Approved HAMIK HARTOUNIAN
Insulation 2/10/2023 Approved HAMIK HARTOUNIAN
Shower Pan 2/28/2023 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/6/2023 Conditional Approval HAMIK HARTOUNIAN
Sewer 4/20/2023 Approved SCOTT FINNILA
Underground Mechanical 4/20/2023 Partial Approval SCOTT FINNILA
Final 5/2/2023 Corrections Issued SCOTT FINNILA
Green Building Final 5/2/2023 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Approved SCOTT FINNILA
Service/Power Release 5/2/2023 Not Ready for Inspection SCOTT FINNILA
Smoke Detectors 5/2/2023 Approved SCOTT FINNILA
Final 5/12/2023 Corrections Issued SCOTT FINNILA
Service/Power Release 5/12/2023 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Final 5/25/2023 Approved SCOTT FINNILA
Final 5/25/2023 OK to Issue CofO SCOTT FINNILA
HVAC-Final 5/25/2023 Approved SCOTT FINNILA
PLUMBING-Final 5/25/2023 Approved SCOTT FINNILA
Service/Power Release 5/25/2023 Approved SCOTT FINNILA