9708 S VAN NESS AVE 90047

Certificate Information: 9708 S VAN NESS AVE 90047

Application / Permit
22010-10000-01061
Plan Check / Job No.
B22LA03888
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW DETACHED FACTORY BUILT ACCESSORY DWELLING UNIT AT REAR PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 KEVIN MORALES
Corrections Issued 3/14/2022 KEVIN MORALES
Applicant returned to address corrections 3/28/2022 KEVIN MORALES
Applicant returned to address corrections 4/15/2022 KEVIN MORALES
Plan Check Approved 5/6/2022 KEVIN MORALES
Issued 5/12/2022 APPLICANT
CofO in Progress 5/19/2023 ENRIQUE MIRELES
CofO in Progress 5/19/2023 ENRIQUE MIRELES
Permit Finaled 5/25/2023 DEROLD HAUFF
CofO Issued 5/25/2023 DEROLD HAUFF
Permit Finaled 5/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/19/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/30/2022 JEANETTE VONG
Sewer availability Cleared 3/30/2022 JEANETTE VONG
Construction near power lines Cleared 4/15/2022 RIDWAN HARDY
Low Impact Development Cleared 4/28/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 4/28/2022 JEANETTE VONG

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 150 E 57TH ST      LOS ANGELES, CA 90011
Engineer Sveiven,, Shane; Lic. No.: C89133 1909 S ALMA STREET      SAN PEDRO, CA 90731

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/19/2022 Approved ENRIQUE MIRELES
Sewer 8/19/2022 Approved ENRIQUE MIRELES
Underground Mechanical 8/19/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/12/2022 Approved ENRIQUE MIRELES
METHANE-Rough 10/12/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 10/12/2022 Approved ENRIQUE MIRELES
HVAC-Rough 11/22/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/16/2022 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 12/16/2022 Approved ENRIQUE MIRELES
Service/Power Release 12/16/2022 Not Ready for Inspection ENRIQUE MIRELES
Final 4/6/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 4/6/2023 Approved ENRIQUE MIRELES
METHANE-Barrier 4/6/2023 Approved ENRIQUE MIRELES
METHANE-Subgrade 4/6/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 4/6/2023 Approved ENRIQUE MIRELES
Smoke Detectors 4/6/2023 Approved ENRIQUE MIRELES
Final 5/12/2023 Corrections Issued ENRIQUE MIRELES
Final 5/18/2023 OK to Issue CofO ENRIQUE MIRELES