1152 E 105TH ST 90002

Certificate Information: 1152 E 105TH ST 90002

Application / Permit
22010-10000-01039
Plan Check / Job No.
B22LA03799
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: New detached Accessory dwelling unit per ordinance
Permit Issued
Issued on 6/27/2023
Issuing Office
Current Status
CofO Issued on 5/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 MONICA RAMIREZ
Corrections Issued 3/30/2022 MONICA RAMIREZ
Quality Review Completed 4/3/2022 HERNAN ARREOLA
Applicant returned to address corrections 5/16/2023 MONICA RAMIREZ
Applicant returned to address corrections 5/26/2023 MONICA RAMIREZ
Plan Check Approved 6/8/2023 MONICA RAMIREZ
Issued 6/27/2023 APPLICANT
CofO in Progress 5/8/2024 BEN MOLSTAD
Permit Finaled 5/24/2024 ANSON MAGLASANG
CofO Issued 5/24/2024 ANSON MAGLASANG
Permit Finaled 5/24/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/25/2022 CINDY QI
Construction near power lines Cleared 8/20/2022 RIDWAN HARDY
Low Impact Development Cleared 10/25/2022 SARAH YOUSSEF
Sewer availability Cleared 3/23/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/13/2023 CINDY QI
Roof/Waste drainage to street Cleared 5/24/2023 CINDY QI
Public Works-Sewers Cleared 5/24/2023 CINDY QI
Public Works-Highway Ded. Cleared 5/24/2023 CINDY QI
Public Works-Open Permits Cleared 5/24/2023 CINDY QI

Contact Information

Architect Yang,, Jaeduk; Lic. No.: C38074 4545 GLENWOOD AVE      LA CRESCENTA, CA 91214
Architect Yang,, Jaeduk; Lic. No.: NA38074       ,
Contractor Empire Construction Services Inc; Lic. No.: 1077736-B       ,
Engineer Kwon,, Ohsung; Lic. No.: NA85429       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/7/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/12/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 8/23/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval JAMES CHAVEZ
HVAC-Rough 8/23/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 8/23/2023 Not Ready for Inspection JAMES CHAVEZ
Insulation 9/8/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 11/27/2023 Corrections Issued JOHN KLARIN
Final 11/27/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready JOHN KLARIN
Service/Power Release 11/27/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 11/27/2023 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 11/27/2023 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 2/12/2024 Partial Approval BEN MOLSTAD
Final 2/12/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 2/12/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Not Required BEN MOLSTAD
Service/Power Release 2/12/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 2/12/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 2/12/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/15/2024 Partial Approval BEN MOLSTAD
Final 2/15/2024 Corrections Issued BEN MOLSTAD
Service/Power Release 2/15/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 2/15/2024 Corrections Issued BEN MOLSTAD
Verify Sprinkler Sign Off 2/15/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 2/21/2024 No Access for Inspection BEN MOLSTAD
Final 2/21/2024 No Access for Inspection BEN MOLSTAD
Service/Power Release 2/21/2024 No Access for Inspection BEN MOLSTAD
Smoke Detectors 2/21/2024 No Access for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 2/21/2024 No Access for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/28/2024 Partial Approval BEN MOLSTAD
Final 2/28/2024 Not Ready for Inspection BEN MOLSTAD
Grading Pre-Inspection 2/28/2024 Approved BEN MOLSTAD
Service/Power Release 2/28/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 2/28/2024 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 2/28/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 3/4/2024 Partial Approval BEN MOLSTAD
Final 3/4/2024 Corrections Issued BEN MOLSTAD
Service/Power Release 3/4/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 3/4/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 4/25/2024 Conditional Approval BEN MOLSTAD
Final 4/25/2024 Corrections Issued BEN MOLSTAD
Service/Power Release 4/25/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 4/25/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 5/7/2024 Approved BEN MOLSTAD
Final 5/7/2024 OK to Issue CofO BEN MOLSTAD
Service/Power Release 5/7/2024 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 5/7/2024 Approved BEN MOLSTAD