147 S SERRANO AVE 90004
Certificate Information: 147 S SERRANO AVE 90004
- Application / Permit
- 22010-10000-01037
- Plan Check / Job No.
- B22LA03797
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) 2 STORY 1 CAR GARAGE W/STORAGE AND REC ROOM TO ADU WITH ATTACHED STORAGE.
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 4/7/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/10/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/12/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/27/2022 | CRYSTEL MAALOUF |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 3/28/2024 | JEFFREY MEAD |
| CofO in Progress | 4/1/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 5/7/2025 | RAUL BARAJAS |
| No Progress | 5/8/2025 | DEROLD HAUFF |
| CofO in Progress | 5/8/2025 | DEROLD HAUFF |
| Permit Finaled | 5/15/2025 | DEROLD HAUFF |
| Permit Finaled | 5/15/2025 | DEROLD HAUFF |
| CofO Issued | 5/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2022 | JEANIE LAM |
| Sewer availability | Cleared | 5/13/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | JEANIE LAM |
| Historic Resource Verification | Cleared | 8/1/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 8/10/2022 | DAVID URITA |
Contact Information
| Contractor | Kim Sang Jin; Lic. No.: 1067789-B | 1801 W PICO BLVD LOS ANGELES, CA 90006 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Approved | JEFFREY MEAD |
| Pre-Inspection | 4/26/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 6/14/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 7/5/2023 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 7/6/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 8/23/2023 | No Access for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | No Access for Inspection | JEFFREY MEAD |
| HVAC-Rough | 8/23/2023 | No Access for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 8/23/2023 | No Access for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/1/2023 | Corrections Issued | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/1/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/1/2023 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 9/6/2023 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 9/6/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/8/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 9/8/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/20/2023 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/20/2023 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 9/20/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/20/2023 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 9/26/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | JEFFREY MEAD |
| Wood Frame | 9/27/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 10/6/2023 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 11/8/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 11/8/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 11/8/2023 | Conditional Approval | JEFFREY MEAD |
| PLUMBING-Final | 11/8/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 11/8/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 1/24/2024 | Corrections Issued | JEFFREY MEAD |
| Smoke Detectors | 1/24/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 1/29/2024 | Corrections Issued | LILIANA PORTILLO |
| Smoke Detectors | 1/29/2024 | Corrections Issued | LILIANA PORTILLO |
| Final | 2/7/2024 | Corrections Issued | AMIR NAZARIAN |
| Smoke Detectors | 2/7/2024 | Approved | AMIR NAZARIAN |
| Final | 3/27/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 5/7/2025 | OK to Issue CofO | RAUL BARAJAS |