9701 W MONTE MAR DR 90035
Certificate Information: 9701 W MONTE MAR DR 90035
- Application / Permit
- 22010-10000-01033
- Plan Check / Job No.
- B22LA03782
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | YOUNG KIM |
| Corrections Issued | 3/16/2022 | YOUNG KIM |
| Quality Review Completed | 3/18/2022 | SAI KHUM |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Applicant returned to address corrections | 6/7/2022 | YOUNG KIM |
| Plan Check Approved | 6/27/2022 | YOUNG KIM |
| Issued | 7/8/2022 | APPLICANT |
| CofO in Progress | 1/24/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/30/2024 | DANIEL ORRANTE |
| CofO Issued | 1/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 3/21/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | JENSON LEE |
| Sewer availability | Cleared | 4/7/2022 | JENSON LEE |
| Low Impact Development | Cleared | 4/8/2022 | ANTHONY VARGAS |
| Miscellaneous | Cleared | 4/8/2022 | RAYMOND MUGAMBWA |
| Hydrant and Access approval | Cleared | 4/30/2022 | JOHN CONNEALLY |
| Specific Plan | Cleared | 5/3/2022 | EDUARDO HERMOSO |
| Trees in Parkway | Cleared | 5/13/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 6/7/2022 | YOUNG KIM |
| Grading Pre-Inspection | Cleared | 6/7/2022 | YOUNG KIM |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | CINDY QI |
Contact Information
| Architect | Leishman,, Thomas Edward; Lic. No.: C15059 | 28100 RIDGEFERN COURT RANCHO PALOS VERDES, CA 90275 |
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | 5967 W 3RD ST #360 LOS ANGELES, CA 90036 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2022 | Partial Inspection | KEVIN SARGSYAN |
| Underground Mechanical | 9/2/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/21/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 10/21/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 10/21/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 1/27/2023 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 5/5/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 5/5/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 5/5/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 5/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 5/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| METHANE-Rough | 5/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Shower Pan | 5/9/2023 | Approved | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 5/9/2023 | Approved | CLAYTON GRAHAM |
| Wood Frame | 5/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | CLAYTON GRAHAM |
| Wood Frame | 5/12/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 6/2/2023 | Conditional Approval | CLAYTON GRAHAM |
| Green Building Rough | 6/2/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | CLAYTON GRAHAM |
| METHANE-Rough | 6/2/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 6/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 6/14/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 6/14/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 6/27/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/4/2024 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 1/4/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 1/4/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 1/4/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/4/2024 | Approved | OGANES TARAKHCHYAN |
| Verify Rec and Parks Fee Memo | 1/10/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/16/2024 | Approved | MEL KHACHATOURIAN |
| Final | 1/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 1/16/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 1/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 1/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 1/19/2024 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 1/22/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 1/23/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |