1964 S THAYER AVE 90025

Certificate Information: 1964 S THAYER AVE 90025

Application / Permit
22010-10000-01031
Plan Check / Job No.
B22LA03774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 8/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 YOUNG KIM
Plans on Hold 3/16/2022 YOUNG KIM
Hold Released 3/24/2022 YOUNG KIM
Corrections Issued 3/24/2022 YOUNG KIM
Quality Review Completed 3/29/2022 SAI KHUM
Building Plans Picked Up 4/6/2022 APPLICANT
Applicant returned to address corrections 7/1/2022 YOUNG KIM
Applicant returned to address corrections 8/8/2022 YOUNG KIM
Plan Check Approved 8/18/2022 YOUNG KIM
Issued 8/18/2022 APPLICANT
Intent to Revoke-Status Void 9/9/2024 ALLEN MANALANSAN
Re-Activate Permit 5/23/2025 ALLEN MANALANSAN
CofO in Progress 6/20/2025 DANIEL VERA
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 4/19/2022 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 5/6/2022 KURT CORRAL
Low Impact Development Cleared 6/14/2022 ROGELIO CORTES
Trees in Parkway Cleared 6/17/2022 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 6/21/2022 TRACY TATE
Permit Cleared 6/21/2022 TRACY TATE
Roof/Waste drainage to street Cleared 6/21/2022 TRACY TATE
Sewer availability Cleared 6/21/2022 TRACY TATE
GPI Written Notices Cleared 7/1/2022 SAI KHUM
Grading Pre-Inspection Cleared 7/1/2022 YOUNG KIM
Specific Plan Cleared 7/15/2022 EDUARDO HERMOSO
Hold Cleared 8/29/2022 PRISCILLA RUIZ

Contact Information

Contractor Lantern Hills Construction Co.; Lic. No.: 1055902-B 10675 WEST PICO BLVD      LOS ANGELES, CA 90064
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2022 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/20/2022 Partial Inspection STEPHANIE SWANSON
Special/Order Compliance 9/20/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/21/2022 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/3/2022 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/7/2022 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 10/7/2022 Partial Approval STEPHANIE SWANSON
METHANE-Barrier 10/7/2022 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Subgrade 10/7/2022 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Subgrade 10/18/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 10/18/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 10/19/2022 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 10/24/2022 Approved STEPHANIE SWANSON
METHANE-Barrier 10/24/2022 Approved STEPHANIE SWANSON
Deputy Wood Construction 11/15/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval STEPHANIE SWANSON
Sewer 12/8/2022 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 4/26/2023 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 4/26/2023 Partial Inspection MICHAEL PELHAM
HVAC-Rough 5/15/2023 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 6/2/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Partial Approval MICHAEL PELHAM
HVAC-Rough 6/2/2023 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 6/2/2023 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 6/14/2023 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 6/14/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 6/14/2023 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval STEPHANIE SWANSON
Green Building Rough 6/14/2023 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 6/14/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 6/14/2023 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Rough 6/14/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/14/2023 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 6/14/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 6/21/2023 Approved STEPHANIE SWANSON
Green Building Rough 6/21/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 6/21/2023 Partial Approval STEPHANIE SWANSON
Special/Order Compliance 6/21/2023 Corrections Issued STEPHANIE SWANSON
Insulation 7/3/2023 Not Ready for Inspection BRENDAN LOONEY
Insulation 7/7/2023 Corrections Issued STEPHANIE SWANSON
Shower Pan 7/10/2023 Approved STEPHANIE SWANSON
Insulation 7/13/2023 Approved STEPHANIE SWANSON
Drywall Nailing 7/19/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/8/2023 Approved STEPHANIE SWANSON
Underground Mechanical 12/19/2023 Partial Approval STEPHANIE SWANSON
Special/Order Compliance 4/1/2024 Not Ready for Inspection STEPHANIE SWANSON
Gas Test 4/5/2024 Partial Approval CARLOS MATAMOROS
Underground Mechanical 4/5/2024 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 4/11/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 5/2/2024 Approved STEPHANIE SWANSON
Underground Mechanical 5/2/2024 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 5/7/2024 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 5/8/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 7/10/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 7/10/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 7/12/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Final 7/17/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 8/9/2024 Approved STEPHANIE SWANSON
HVAC-Final 8/9/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Final 8/20/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Final 8/20/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Final 9/4/2024 Approved STEPHANIE SWANSON
Special/Order Compliance 9/9/2024 Partial Inspection MICHAEL PELHAM
Final 5/30/2025 Corrections Issued SEAN HAUPT
Green Building Final 5/30/2025 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 5/30/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved SEAN HAUPT
Service/Power Release 5/30/2025 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 5/30/2025 Not Ready for Inspection SEAN HAUPT
Final 6/10/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 6/10/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 6/10/2025 Not Ready for Inspection DANIEL VERA
Smoke Detectors 6/10/2025 Not Ready for Inspection DANIEL VERA
Final 6/16/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 6/16/2025 Approved DANIEL VERA
HVAC-Final 6/16/2025 Corrections Issued DANIEL VERA
Service/Power Release 6/16/2025 Not Ready for Inspection DANIEL VERA
Smoke Detectors 6/16/2025 Approved DANIEL VERA
Final 6/20/2025 OK to Issue CofO DANIEL VERA
PLUMBING-Final 6/20/2025 Approved DANIEL VERA
Service/Power Release 6/20/2025 Approved DANIEL VERA